QNI Minor testing (NSW to Qld) 12th August 2024
Refer to market notice 116052
There is an opportunity for testing QNI Minor for flows from NSW to Qld up to 850 MW on Monday 12th August 2024 from 1100 to 1700hrs.
This test includes a trip and reclose of a line in northern NSW.
Please also refer to the published formal QNI minor testing information at the following link:
https://www.aemo.com.au/consultations/current-and-closed-consultations/qld-to-nsw-interconnector-qni-upgrade
Ben Blake
AEMO Operations
NON-CONFORMANCE Region SA1 Sunday, 11 August 2024
NON-CONFORMANCE SA1 Region Sunday, 11 August 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: OSB-AG
Duration: 11/08/2024 15:30 to 11/08/2024 15:40
Amount: 52 MW
Constraint: NC-S_OSB-AG
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region VIC1 Sunday, 11 August 2024
NON-CONFORMANCE VIC1 Region Sunday, 11 August 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: LYA4
Duration: 11/08/2024 13:05 to 11/08/2024 13:35
Amount: -61 MW
Constraint: NC-V_LYA4
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Saturday, 10 August 2024
NON-CONFORMANCE QLD1 Region Saturday, 10 August 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_1
Duration: 10/08/2024 01:05 to 10/08/2024 01:25
Amount: -47 MW
Constraint: NC-Q_MPP_1
Auto-generated on behalf of Manager NEM Real Time Operations
CHG0091753 | Completed | Pre-Production | Pre production Gas Supply Hub (GSH) Environment Outage
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Gas Supply Hub
Change Title: Pre production Gas Supply Hub (GSH) Environment Outage
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
CHG0095132 | Production | AEMO will be undertaking maintenance activities on the DWGM system
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Cohesity
Change Title: AEMO will be undertaking maintenance activities on the DWGM system
Change Start Date & Time: 13/08/2024 22:30:42 AEST
Change End Date & Time: 14/08/2024 08:30:42 AEST
Outage Start Date & Time:
Outage End Date & Time:
Environment: Production
Participant Impact and Requirements:
AEMO will be undertaking maintenance activities on the DWGM system. Whilst no outage is expected there is potential for transient performance degradation during the change.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
CHG0095134 | Production | AEMO will be undertaking maintenance activities on the SMP system
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Cohesity
Change Title: AEMO will be undertaking maintenance activities on the SMP system
Change Start Date & Time: 11/08/2024 15:00:57 AEST
Change End Date & Time: 12/08/2024 01:00:57 AEST
Outage Start Date & Time:
Outage End Date & Time:
Environment: Production
Participant Impact and Requirements: AEMO will be undertaking maintenance activities on the SMP system. Whilst no outage is expected there is potential for transient performance degradation during the change.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
Network Augmentation Commissioned - VIC Region - 07/08/2024
Network Augmentation Commissioned - VIC Region - 07/08/2024
Cressy - Golden Plains No. 2 220 kV Line has been commissioned.
Manager NEM Real Time Operations
CHG0087952 | Pre-Production | Retail Pre-Production Data refresh (CATS and EMDM)
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MSATS - Consumer Administration and Transfer Solution(CATS)
Change Title: Retail Pre-Production Data refresh (CATS and EMDM)
Change Start Date & Time: 12/08/2024 09:00:00 AEST
Change End Date & Time: 16/08/2024 18:00:00 AEST
Outage Start Date & Time:
Outage End Date & Time:
Environment: Pre-Production
Participant Impact and Requirements: MSATS (preprod), CDR (preprod) and CDP (preprod) will be unavailble between 12th Aug to 16th Aug cob
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?d=pp_services_status for any planned/unplanned maintenance activities .