[EventId:202410030905_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 03 October 2024 09:05
Issued by Australian Energy Market Operator Ltd at 0905 hrs on 3 October 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 3 October 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 0905 hrs on 3 October 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 08/10/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 118548 has been updated at 1400 hrs 02/10/2024 to the following:
1. From 1730 hrs to 1930 hrs 08/10/2024.
The forecast capacity reserve requirement is 1107 MW.
The minimum capacity reserve available is 797 MW.
2. From 2100 hrs to 2130 hrs 08/10/2024.
The forecast capacity reserve requirement is 1118 MW.
The minimum capacity reserve available is 972 MW.
AEMO Operations
[EventId:202410021230_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 02 October 2024 12:30
Issued by Australian Energy Market Operator Ltd at 1230 hrs on 2 October 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 2 October 2024.
Refer to market notice: 118557
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1230 hrs on 2 October 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202410021110_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 02 October 2024 11:10
Issued by Australian Energy Market Operator Ltd at 1110 hrs on 2 October 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 2 October 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1110 hrs on 2 October 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202410021100_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 02 October 2024 11:00
Issued by Australian Energy Market Operator Ltd at 1100 hrs on 2 October 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 2 October 2024.
Refer to market notice: 118554
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1100 hrs on 2 October 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202410020950_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 02 October 2024 09:50
Issued by Australian Energy Market Operator Ltd at 0950 hrs on 2 October 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 2 October 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 0950 hrs on 2 October 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 08/10/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following periods:
1. From 1730 hrs to 2030 hrs 08/10/2024.
The forecast capacity reserve requirement is 1108 MW.
The minimum capacity reserve available is 668 MW.
2. From 2100 hrs to 2200 hrs 08/10/2024.
The forecast capacity reserve requirement is 1120 MW.
The minimum capacity reserve available is 816 MW.
AEMO Operations
[EventId:202409301530_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 30 September 2024 15:30
Issued by Australian Energy Market Operator Ltd at 1530 hrs on 30 September 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 30 September 2024.
Refer to market notice: 118533
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1530 hrs on 30 September 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202409301435_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 30 September 2024 14:35
Issued by Australian Energy Market Operator Ltd at 1435 hrs on 30 September 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 30 September 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1435 hrs on 30 September 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.