Market Notices

117388SETTLEMENTS RESIDUE20/07/2024 02:30:21 PM

[EventId:202407201430_NRM_VIC1_NSW1_stopped] NEGRES CONSTRAINT NRM_VIC1_NSW1 ceased operating from 20 July 2024 14:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1430 hrs on 20 July 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to NSW - 20 July 2024.

Refer to market notice: 117382

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to NSW directional interconnector.

The negative residue constraint NRM_VIC1_NSW1 ceased operating at 1430 hrs on 20 July 2024.

This is an AEMO autogenerated Market Notice.
117382SETTLEMENTS RESIDUE20/07/2024 01:30:31 PM

[EventId:202407201330_NRM_VIC1_NSW1_started] NEGRES CONSTRAINT NRM_VIC1_NSW1 started operating from 20 July 2024 13:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1330 hrs on 20 July 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to NSW - 20 July 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to NSW directional interconnector.

The negative residue constraint set NRM_VIC1_NSW1 commenced operating from 1330 hrs on 20 July 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
117356GENERAL NOTICE18/07/2024 09:06:38 PM

Network Augmentation Commissioned - VIC Region - 18/07/2024

AEMO ELECTRICITY MARKET NOTICE

Network Augmentation Commissioned - VIC Region - 18/07/2024

At 2044 hrs 18,07/2024, Cressy Terminal Station has been cut into the existing Moorabool - Haunted Gully No.1 500 kV line to form the following circuits:

Cressy - Haunted Gully No 1 500 kV line
Cressy - Moorabool No 1 500 kV line

Manager NEM Real Time Operations
117321LOAD SHED08/07/2024 07:08:46 PM

Load Shedding Direction in the NSW Region

AEMO ELECTRICITY MARKET NOTICE

Load Shedding Direction in the NSW Region

AEMO has directed load shedding commencing at 1817 hrs 08/07/2024
in the NSW region

to maintain power system security.

The direction was issued under section 116 of the NEL, and was a clause 4.8.9 instruction under the NER.

Manager NEM Real Time Operations
117285SETTLEMENTS RESIDUE03/07/2024 05:55:22 PM

[EventId:202407031755_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 03 July 2024 17:55

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1755 hrs on 3 July 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 3 July 2024.

Refer to market notice: 117283

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1755 hrs on 3 July 2024.

This is an AEMO autogenerated Market Notice.
117283SETTLEMENTS RESIDUE03/07/2024 05:30:25 PM

[EventId:202407031730_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 03 July 2024 17:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1730 hrs on 3 July 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 3 July 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1730 hrs on 3 July 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
117238GENERAL NOTICE28/06/2024 08:43:51 AM

Fast Frequency Response Market - Dispatch of R1 and L1 FCAS in the SA region during island conditions from 1 July 2024

AEMO ELECTRICITY MARKET NOTICE

From 1 July 2024 AEMO will dispatch R1 and L1 FCAS locally in the SA region during conditions of actual islanding of the SA region.

This follows the end of contracts for Fast Frequency Response (FFR) in the SA region.

The dispatch of R1 and L1 FCAS under these island conditions will not be capped.

These changes are only applicable for conditions of actual SA islanding from the rest of the NEM.

No other changes to the dispatch of R1 and L1 FCAS will be made on this date.

For information on the Fast Frequency Response (FFR) initiative please visit the website at: https://www.aemo.com.au/initiatives/major-programs/fast-frequency-response

Andrew Groom
AEMO Operations
117210POWER SYSTEM EVENTS27/06/2024 09:01:59 AM

Non-credible contingency event - NSW region - 27/06/2024

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - NSW region - 27/06/2024

At 0845 hrs the Sydney West No.1 330 kV SVC tripped during switching for planned outage of Sydney West No.4 330/132 kV transformer.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.


Manager NEM Real Time Operations
117132POWER SYSTEM EVENTS25/06/2024 10:20:35 AM

Non-credible contingency event - NSW region - 25/06/2024

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - NSW region - 25/06/2024

At 0901 hrs the Sydney West No.1 330 kV SVC tripped during switching for planned outage of Sydney West No.4 330/132 kV transformer.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.

AEMO will not reclassify this event as a credible contingency event.

Manager NEM Real Time Operations
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm