125392RECLASSIFY CONTINGENCY08/03/2025 02:37:05 PM

Reclassification of a Non-Credible Contingency Event: Chalumbin - Turkinje No.7165 132 kV line and Chalumbin - Turkinje No.7166 132 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Chalumbin - Turkinje No.7165 132 kV and Chalumbin - Turkinje No.7166 132 kV

Duration: 08/03/2025 14:37 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
     
125389PRICES UNCHANGED08/03/2025 01:30:25 PM

[EventId:202503081305_confirmed] Prices for interval 08-Mar-2025 13:05 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1330 hrs on 8 March 2025

PRICES ARE NOW CONFIRMED for trading interval 08-Mar-2025 13:05.

In accordance with Market Notice 125376 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
125388PRICES UNCHANGED08/03/2025 01:30:25 PM

[EventId:202503081330_confirmed] Prices for interval 08-Mar-2025 13:30 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1330 hrs on 8 March 2025

PRICES ARE NOW CONFIRMED for trading interval 08-Mar-2025 13:30.

In accordance with Market Notice 125383 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
125387PRICES UNCHANGED08/03/2025 01:30:25 PM

[EventId:202503081325_confirmed] Prices for interval 08-Mar-2025 13:25 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1330 hrs on 8 March 2025

PRICES ARE NOW CONFIRMED for trading interval 08-Mar-2025 13:25.

In accordance with Market Notice 125382 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
125386PRICES UNCHANGED08/03/2025 01:30:25 PM

[EventId:202503081320_confirmed] Prices for interval 08-Mar-2025 13:20 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1330 hrs on 8 March 2025

PRICES ARE NOW CONFIRMED for trading interval 08-Mar-2025 13:20.

In accordance with Market Notice 125381 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
125385PRICES UNCHANGED08/03/2025 01:30:26 PM

[EventId:202503081315_confirmed] Prices for interval 08-Mar-2025 13:15 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1330 hrs on 8 March 2025

PRICES ARE NOW CONFIRMED for trading interval 08-Mar-2025 13:15.

In accordance with Market Notice 125379 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
125384PRICES UNCHANGED08/03/2025 01:30:26 PM

[EventId:202503081310_confirmed] Prices for interval 08-Mar-2025 13:10 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1330 hrs on 8 March 2025

PRICES ARE NOW CONFIRMED for trading interval 08-Mar-2025 13:10.

In accordance with Market Notice 125378 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
125365RECLASSIFY CONTINGENCY07/03/2025 03:04:25 PM

Cancellation - Reclassification of a Non-Credible Contingency Event: Darling Downs Power Station in Queensland Region - 06/03/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation - Reclassification of a Non-Credible Contingency Event: Darling Downs Power Station in Queensland Region - 06/03/2025

Refer to MN 125332

AEMO no longer considers the simultaneous trip of all the generators at Darling Downs Power Station as a credible contingency event.

Accordingly, its classification has reverted to a non-credible contingency event.

Constraint set Q-DARLING_DOWNS_N-2 revoked from 1500 hrs 07/03/2025

Manager NEM Real Time Operations
     
125355POWER SYSTEM EVENTS07/03/2025 06:40:37 AM

Non-credible contingency event - NSW region - 07/03/2025

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - NSW region - 07/03/2025

At 0612 hrs the following plant tripped.

Lismore132 - Mullumbimby 9U6 132kV Line
Lismore132 - Mullumbimby 9U7 132kV Line
Ewingsdale - Mullumbimby 9G5 132kV Line
No 1 and 2 cables of Directlink

AEMO did not instruct load shedding.

Approximately 7MW of bulk electrical load has been disconnected.

The cause of this non credible contingency event is not known at this stage.


Manager NEM Real Time Operations
     