122354PRICES UNCHANGED21/12/2024 01:00:22 PM

[EventId:202412211245_confirmed] Prices for interval 21-Dec-2024 12:45 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1300 hrs on 21 December 2024

PRICES ARE NOW CONFIRMED for trading interval 21-Dec-2024 12:45.

In accordance with Market Notice 122348 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
122353PRICES UNCHANGED21/12/2024 01:03:56 PM

[EventId:202412211235_confirmed] Prices for interval 21-Dec-2024 12:35 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1300 hrs on 21 December 2024

PRICES ARE NOW CONFIRMED for trading interval 21-Dec-2024 12:35.

In accordance with Market Notice 122345 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
122346SETTLEMENTS RESIDUE21/12/2024 12:30:25 PM

[EventId:202412211230_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 21 December 2024 12:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1230 hrs on 21 December 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 21 December 2024.

Refer to market notice: 122343

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1230 hrs on 21 December 2024.

This is an AEMO autogenerated Market Notice.
     
122344MINIMUM SYSTEM LOAD21/12/2024 08:57:33 AM

Cancellation of Forecast Minimum System Load (MSL) MSL1 event in the VIC Region on 21/12/2024.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Forecast Minimum System Load (MSL) MSL1 event in the VIC Region on 21/12/2024.

Cancellation - Forecast MSL1- VIC Region at 0900 hrs 21/12/2024.

Refer to Market Notice 122109 for MSL1.

Manager NEM Real Time Operations
     
122343SETTLEMENTS RESIDUE21/12/2024 08:00:20 AM

[EventId:202412210800_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 21 December 2024 08:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0800 hrs on 21 December 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 21 December 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 0800 hrs on 21 December 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
122341MINIMUM SYSTEM LOAD21/12/2024 03:08:02 AM

Forecast Minimum System Load MSL2 condition in the VIC Region on 22/12/2024

AEMO ELECTRICITY MARKET NOTICE
Forecast Minimum System Load MSL2 condition in the VIC Region on 22/12/2024

AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC on 22/12/2024.

Minimum System Load (MSL) conditions are forecast when regional demand is less than the relevant MSL threshold. The advisory MSL thresholds are:
- MSL1 - 1825 MW
- MSL2 - 1325 MW
- MSL3 - 825 MW

The regional demand is forecast to be below the MSL2 threshold for the following period[s]:
- From 1200 hrs 22/12/2024 to 1330 hrs 22/12/2024. Minimum regional demand is forecast to be 1276 MW at 1300 hrs.

Forecast regional demand (DEMAND50) is published in Short Term and Pre-Dispatch PASA region solution reports available on Market Data NEMWEB: https://aemo.com.au/en/energy-systems/electricity/national-electricity-market-nem/data-nem/market-data-nemweb .


Manager NEM Real Time Operations
     
122340MARKET INTERVENTION21/12/2024 03:54:16 AM

Cancellation: Direction issued to: Synergen Power Pty Limited - MINTARO MINTARO GAS

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: Synergen Power Pty Limited - MINTARO MINTARO GAS

Refer to Market Notice 122297

Direction is cancelled from: 0400 hrs 21/12/2024

Manager NEM Real Time Operations
     
122327SETTLEMENTS RESIDUE20/12/2024 04:30:28 PM

[EventId:202412201630_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 20 December 2024 16:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1630 hrs on 20 December 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 20 December 2024.

Refer to market notice: 122309

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1630 hrs on 20 December 2024.

This is an AEMO autogenerated Market Notice.
     
122312MARKET INTERVENTION20/12/2024 02:45:17 PM

Direction - SA region to AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region to AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 122279


In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN at 1445 hrs 20/12/2024
Type of resource: generating unit
Required actions: Synchronise and follow dispatch targets at 0400 hrs 21/12/2024
Services provided: Voltage Control
Circumstances necessitating the Direction:Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 0400 hrs 22/12/2024 / further notice.

AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     
X