Filter by category
Filter by Date
NEM Local Temperature Alerts for SA, VIC from 16 Dec 2024 to 20 Dec 2024
AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.
SA
Clare High School (39+ Deg C): 16th Dec
Port Augusta Ap (39+ Deg C): 16th Dec
VIC
Ararat Prison (39+ Deg C): 16th Dec
Latrobe Valley Ap (39+ Deg C): 16th Dec
Melbourne Olympic Park (39+ Deg C): 16th Dec
Mildura Ap (39+ Deg C): 16th Dec, 20th Dec
Mortlake (39+ Deg C): 16th Dec
The NEM Local Temperature Alert Levels are:
Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.
AEMO requests Market Participants to:
1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,
2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.
Further information is available at:
https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts
AEMO Operations Planning
[EventId:202412160905_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 16 December 2024 09:05
Issued by Australian Energy Market Operator Ltd at 0905 hrs on 16 December 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 16 December 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 0905 hrs on 16 December 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 16/12/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 121949 has been updated at
1900 hrs to the following:
[1.] From 1700 hrs 16/12/2024 to 1800 hrs 16/12/2024.
The forecast capacity reserve requirement is 1350 MW.
The minimum capacity reserve available is 1143 MW.
Manager NEM Real Time Operations
[EventId:202412151845_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 15 December 2024 18:45
Issued by Australian Energy Market Operator Ltd at 1845 hrs on 15 December 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 15 December 2024.
Refer to market notice: 121984
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1845 hrs on 15 December 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202412151705_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 15 December 2024 17:05
Issued by Australian Energy Market Operator Ltd at 1705 hrs on 15 December 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 15 December 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1705 hrs on 15 December 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202412151600_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 15 December 2024 16:00
Issued by Australian Energy Market Operator Ltd at 1600 hrs on 15 December 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 15 December 2024.
Refer to market notice: 121959
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1600 hrs on 15 December 2024.
This is an AEMO autogenerated Market Notice.
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0130 hrs 17/12/2024.
The foreseeable circumstance requiring the need for intervention is Voltage.
Manager NEM Real Time Operations
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 17/12/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 121899 has been updated at 1430 hrs 15/12/2024 to the following:
[1.] From 1400 hrs 17/12/2024 to 1430 hrs 17/12/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 1307 MW.
[2.] From 2130 hrs 17/12/2024 to 2230 hrs 17/12/2024.
The forecast capacity reserve requirement is 1859 MW.
The minimum capacity reserve available is 1203 MW.
AEMO Operations
[EventId:202412151400_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 15 December 2024 14:00
Issued by Australian Energy Market Operator Ltd at 1400 hrs on 15 December 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 15 December 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1400 hrs on 15 December 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.