Reclassification of a Non-Credible Contingency Event: Eraring Power Station in NSW Region 23/09/2024
Reclassification of a Non-Credible Contingency Event: Eraring Power Station in NSW Region 23/09/2024
Based on advice from the asset owner, AEMO has declared the simultaneous trip of Eraring Power Station Units 2 and 4 as a credible contingency event.
AEMO considers the simultaneous trip of those generators to now be more likely.
AEMO has reclassified this as a credible contingency event from 1000 hrs 23/09/2024.
To manage power system security constraint set N-ERARING_N-2 invoked from 1000 hrs 23/09/2024 until further notice.
Manager NEM Real Time Operations
Cancellation of a Non-Credible Contingency Event: Farrell-John Butters line and Farrell-Rosebery-Newton-Queenstown line in TAS1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: TAS1
Lines: Farrell-John Butters and Farrell-Rosebery-Newton-Queenstown
Cancellation time: 21/09/2024 00:14
Constraint set(s) revoked:
NONE
Refer AEMO Electricity Market Notice 118345
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation of Reclassification of a Non-Credible Contingency Event: Gordon - Chapel Street No.1 and No.2 220 kV lines in TAS1 due to Lightning
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning.
AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: TAS
Lines: Gordon - Chapel Street No.1 and No.2 220 kV lines
Cancellation time: 0020 hrs 21/09/2024
Constraint sets revoked: F-T-CSGO and T-CSGO_N-2
Manager NEM Real Time Operations
Cancellation of a Non-Credible Contingency Event: Farrell - Reece No.1 220 kV line and Farrell - Reece No.2 220 kV line in TAS1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: TAS1
Lines: Farrell - Reece No.1 220 kV and Farrell - Reece No.2 220 kV
Cancellation time: 21/09/2024 00:09
Constraint set(s) revoked:
F-T-FARE_N-2 Constraint set contains the following interconnector(s) on the left hand side:
T-V-MNSP1
Refer AEMO Electricity Market Notice 118347
Auto-generated on behalf of Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Farrell - Reece No.1 220 kV line and Farrell - Reece No.2 220 kV line in TAS1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: TAS1
Lines: Farrell - Reece No.1 220 kV and Farrell - Reece No.2 220 kV
Duration: 20/09/2024 19:06 until further notice
Constraint set(s) invoked:
F-T-FARE_N-2 Constraint set contains the following interconnector(s) on the left hand side:
T-V-MNSP1
Auto-generated on behalf of Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Farrell-John Butters line and Farrell-Rosebery-Newton-Queenstown line in TAS1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: TAS1
Lines: Farrell-John Butters and Farrell-Rosebery-Newton-Queenstown
Duration: 20/09/2024 18:09 until further notice
Constraint set(s) invoked:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Gordon - Chapel Street No.1 and No.2 220 kV lines in TAS1 due to Lightning
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning.
AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: TAS
Lines: Gordon - Chapel Street No.1 and No.2 220 kV lines
Duration: 1745 hrs 20/09/2024 until further notice
Constraint set(s) invoked: F-T-CSGO and T-CSGO_N-2
Manager NEM Real Time Operations
Update to system normal constraint equation in NSW for transient voltage stability in south-west NSW
Refer to market notice 92840.
Transgrid has advised AEMO of an update to the transient voltage stability limit in south-west NSW for loss of Darlington Point to Wagga (63) 330 kV line. The limit will include terms for the Darlington Point and Riverina BESS.
The following constraint equation will be updated with the above changes at 1100 hrs Friday 20th September 2024.
N::N_NIL_63
For full details on the formulation, the new constraint equation has now been loaded into AEMO's pre-production systems.
For further details on these constraint equation please contact ben.blake@aemo.com.au
Ben Blake
AEMO Operations
Cancellation of a Non-Credible Contingency Event: Farrell-John Butters line and Farrell-Rosebery-Newton-Queenstown line in TAS1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: TAS1
Lines: Farrell-John Butters and Farrell-Rosebery-Newton-Queenstown
Cancellation time: 19/09/2024 12:34
Constraint set(s) revoked:
NONE
Refer AEMO Electricity Market Notice 118317
Auto-generated on behalf of Manager NEM Real Time Operations