Planned outage of Tailem Bend - South East 275 kV transmission line in the South Australia region beginning on 20/09/2024
The Tailem Bend - South East No 1 275 kV line in the South Australian (SA) region is planned to be out of service from 2100 hrs on 20/09/2024 to 0530 hrs on 21/09/2024.
A credible contingency event during this planned outage could cause synchronous separation of the SA region from the rest of the NEM.
During this planned outage:
- Power transfer will be restricted across the VIC - SA interconnector (Heywood interconnector); and
- Post contingent FCAS will be sourced within SA following Separation event.
Refer AEMO Network Outage Schedule (NOS) for further details.
AEMO Operations
[EventId:202409111325_review] Prices for interval 11-Sep-2024 13:25 are subject to review
Issued by Australian Energy Market Operator Ltd at 1320 hrs on 11 September 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 11-Sep-2024 13:25.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202409111320_review] Prices for interval 11-Sep-2024 13:20 are subject to review
Issued by Australian Energy Market Operator Ltd at 1315 hrs on 11 September 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 11-Sep-2024 13:20.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202409111315_review] Prices for interval 11-Sep-2024 13:15 are subject to review
Issued by Australian Energy Market Operator Ltd at 1310 hrs on 11 September 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 11-Sep-2024 13:15.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202409111310_review] Prices for interval 11-Sep-2024 13:10 are subject to review
Issued by Australian Energy Market Operator Ltd at 1305 hrs on 11 September 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 11-Sep-2024 13:10.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202409111305_review] Prices for interval 11-Sep-2024 13:05 are subject to review
Issued by Australian Energy Market Operator Ltd at 1300 hrs on 11 September 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 11-Sep-2024 13:05.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202409111300_review] Prices for interval 11-Sep-2024 13:00 are subject to review
Issued by Australian Energy Market Operator Ltd at 1255 hrs on 11 September 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 11-Sep-2024 13:00.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
Network Augmentation Commissioned - NSW Region - 10/09/2024
Network Augmentation Commissioned - NSW Region - 10/09/2024
At 1750 hrs, the following equipment at Buronga 330 kV substation has been commissioned:
1) Buronga 330 kV A bus.
2) Buronga 330 kV B bus.
3) Buronga No 1 330 kV capacitor.
4) Buronga No 2 330 kV capacitor.
5) Buronga No 7 330/220 kV transformer.
Manager NEM Real Time Operations
[EventId:202409081835_review] Prices for interval 08-Sep-2024 18:35 are subject to review
Issued by Australian Energy Market Operator Ltd at 1830 hrs on 8 September 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 08-Sep-2024 18:35.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.