Non-credible contingency event - QLD region - 27/07/2024
Non-credible contingency event - QLD region - 27/07/2024
At 0951 hrs the H3 Goodna No. 2 275kV Bus and the H3 Goodna No. 1 275/132kV transformer tripped.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the NSW region - 03/07/2024
Cancellation of Actual (LOR1) condition in the NSW region - 03/07/2024
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.117284 is cancelled at 2010 hrs 03/07/2024.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 03/07/2024
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 03/07/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1930 hrs
The capacity reserve requirement is 1400 MW
The minimum capacity reserve available is 766 MW
Manager NEM Real Time Operations
[EventId:202406271800_review] Prices for interval 27-Jun-2024 18:00 are subject to review
Issued by Australian Energy Market Operator Ltd at 1755 hrs on 27 June 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 27-Jun-2024 18:00.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202406271755_review] Prices for interval 27-Jun-2024 17:55 are subject to review
Issued by Australian Energy Market Operator Ltd at 1750 hrs on 27 June 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 27-Jun-2024 17:55.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202406271750_review] Prices for interval 27-Jun-2024 17:50 are subject to review
Issued by Australian Energy Market Operator Ltd at 1745 hrs on 27 June 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 27-Jun-2024 17:50.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202406271745_review] Prices for interval 27-Jun-2024 17:45 are subject to review
Issued by Australian Energy Market Operator Ltd at 1740 hrs on 27 June 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 27-Jun-2024 17:45.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202406271740_review] Prices for interval 27-Jun-2024 17:40 are subject to review
Issued by Australian Energy Market Operator Ltd at 1735 hrs on 27 June 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 27-Jun-2024 17:40.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202406271735_review] Prices for interval 27-Jun-2024 17:35 are subject to review
Issued by Australian Energy Market Operator Ltd at 1730 hrs on 27 June 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 27-Jun-2024 17:35.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.