Market Notices

117556PRICES UNCHANGED05/08/2024 05:01:33 PM

[EventId:202408051645_confirmed] Prices for interval 05-Aug-2024 16:45 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1700 hrs on 5 August 2024

PRICES ARE NOW CONFIRMED for trading interval 05-Aug-2024 16:45.

In accordance with Market Notice 117550 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
117555PRICES UNCHANGED05/08/2024 05:00:16 PM

[EventId:202408051635_confirmed] Prices for interval 05-Aug-2024 16:35 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1700 hrs on 5 August 2024

PRICES ARE NOW CONFIRMED for trading interval 05-Aug-2024 16:35.

In accordance with Market Notice 117548 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
117508GENERAL NOTICE30/07/2024 02:45:25 PM

Increase to QNI limit to next hold point of 1400 MW Qld to NSW

AEMO ELECTRICITY MARKET NOTICE

Refer to market notices 117060.

AEMO, TransGrid, Powerlink have reviewed the test results following the QNI minor testing on 19th June 2024. The next hold point can now be released.

The hold point of 1400 MW from Qld to NSW will be implemented as of 1000 hrs 31st July 2024.

Please also refer to the published formal QNI minor testing information at the following link:
https://www.aemo.com.au/consultations/current-and-closed-consultations/qld-to-nsw-interconnector-qni-upgrade

Ben Blake
AEMO Operations
117503POWER SYSTEM EVENTS30/07/2024 07:07:11 AM

Non-credible contingency event - QLD region - 30/07/2024

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - QLD region - 30/07/2024

At 0537 hrs the Darling Downs Power Station GT1, GT3 and and the steam turbine tripped from 484 MW.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.


Manager NEM Real Time Operations
117500POWER SYSTEM EVENTS28/07/2024 05:14:14 PM

Update - Non-credible contingency event - QLD region - 27/07/2024

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - QLD region - 27/07/2024

Refer AEMO Electricity Market Notice 117487

At 1702 hrs the H38 Goodna No. 2 275kV Bus and the H38 Goodna No. 1 275/132kV transformer was returned to service.

The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.

AEMO will not reclassify this event as a credible contingency event.

Manager NEM Real Time Operations
117487POWER SYSTEM EVENTS27/07/2024 10:52:18 AM

Correction - Non-credible contingency event - QLD region - 27/07/2024

AEMO ELECTRICITY MARKET NOTICE.

Correction to Market Notice 117486

Non-credible contingency event - QLD region - 27/07/2024

At 0951 hrs the H38 Goodna No. 2 275kV Bus and the H38 Goodna No. 1 275/132kV transformer tripped.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.

Manager NEM Real Time Operations
117486POWER SYSTEM EVENTS27/07/2024 10:26:53 AM

Non-credible contingency event - QLD region - 27/07/2024

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - QLD region - 27/07/2024

At 0951 hrs the H3 Goodna No. 2 275kV Bus and the H3 Goodna No. 1 275/132kV transformer tripped.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.

Manager NEM Real Time Operations
117466GENERAL NOTICE30/07/2024 09:20:28 PM

Network Augmentation Commissioned - VIC Region - 30/07/2024

AEMO ELECTRICITY MARKET NOTICE

Network Augmentation Commissioned - VIC Region - 30/07/2024

Cressy Terminal Station has been cut into the existing Moorabool - Mortlake No.2 500 kV line to form the following circuits:

Cressy - Mortlake No.2 500 kV line
Cressy - Moorabool No.2 500 kV line

Manager NEM Real Time Operations
117356GENERAL NOTICE18/07/2024 09:06:38 PM

Network Augmentation Commissioned - VIC Region - 18/07/2024

AEMO ELECTRICITY MARKET NOTICE

Network Augmentation Commissioned - VIC Region - 18/07/2024

At 2044 hrs 18,07/2024, Cressy Terminal Station has been cut into the existing Moorabool - Haunted Gully No.1 500 kV line to form the following circuits:

Cressy - Haunted Gully No 1 500 kV line
Cressy - Moorabool No 1 500 kV line

Manager NEM Real Time Operations
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm