[EventId:202501141805_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 14 January 2025 18:05
Issued by Australian Energy Market Operator Ltd at 1805 hrs on 14 January 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 14 January 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1805 hrs on 14 January 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 14/01/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 1800 hrs 14/01/2025 to 1900 hrs 14/01/2025.
The forecast capacity reserve requirement is 1580 MW.
The minimum capacity reserve available is 1423 MW.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 15/01/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 1630 hrs 15/01/2025 to 1830 hrs 15/01/2025.
The forecast capacity reserve requirement is 1720 MW.
The minimum capacity reserve available is 1570 MW.
Manager NEM Real Time Operations
[EventId:202501141300_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 14 January 2025 13:00
Issued by Australian Energy Market Operator Ltd at 1300 hrs on 14 January 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 14 January 2025.
Refer to market notice: 123198
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1300 hrs on 14 January 2025.
This is an AEMO autogenerated Market Notice.
[EventId:202501141135_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 14 January 2025 11:35
Issued by Australian Energy Market Operator Ltd at 1135 hrs on 14 January 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 14 January 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1135 hrs on 14 January 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
NEM Local Temperature Alerts for QLD, SA, VIC from 14 Jan 2025 to 18 Jan 2025
AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.
QLD
Rockhampton Ap (39+ Deg C): 16th Jan
SA
Port Augusta Ap (39+ Deg C): 14th Jan
VIC
Mildura Ap (39+ Deg C): 14th Jan
The NEM Local Temperature Alert Levels are:
Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.
AEMO requests Market Participants to:
1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,
2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.
Further information is available at:
https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts
AEMO Operations Planning
[EventId:202501131945_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 13 January 2025 19:45
Issued by Australian Energy Market Operator Ltd at 1945 hrs on 13 January 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 13 January 2025.
Refer to market notice: 123173
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1945 hrs on 13 January 2025.
This is an AEMO autogenerated Market Notice.
[EventId:202501131705_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 13 January 2025 17:05
Issued by Australian Energy Market Operator Ltd at 1705 hrs on 13 January 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 13 January 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1705 hrs on 13 January 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 13/01/2025
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 123157 has been updated at 1630 hrs to the following:
[1.] From 1630 hrs 13/01/2025 to 1700 hrs 13/01/2025.
The forecast capacity reserve requirement is 1372 MW.
The minimum capacity reserve available is 1061 MW.
[2.] From 1900 hrs 13/01/2025 to 2000 hrs 13/01/2025.
The forecast capacity reserve requirement is 1603 MW.
The minimum capacity reserve available is 1214 MW.