124219RESERVE NOTICE05/02/2025 08:37:04 PM

Cancellation of Actual (LOR1) condition in the NSW region - 05/02/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 05/02/2025

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.124200 is cancelled at 2019 hrs 05/02/2025.

Manager NEM Real Time Operations
     
124200RESERVE NOTICE05/02/2025 05:52:02 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 05/02/2025

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 05/02/2025

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1900 hrs

The capacity reserve requirement is 1430 MW
The minimum capacity reserve available is 1214 MW

Manager NEM Real Time Operations
     
124180GENERAL NOTICE05/02/2025 03:16:32 PM

Update - Vulnerable lines in TAS region

AEMO ELECTRICITY MARKET NOTICE.

Update - Lightning vulnerable lines in TAS region
Refer to AEMO Electricity Market Notice 124044
At 1410 hrs 03/02/2025 the Farrell - Reece No.1 and No.2 220 kV lines lines tripped.
The cause of the trip was identified as due to lightning.
In accordance with SO_OP_3715, AEMO now considers the Farrell - Reece No.1 and No.2 220 kV lines to be vulnerable with a category of probable due to lightning.

Manager NEM Real Time Operations
     
124179RESERVE NOTICE05/02/2025 02:54:25 PM

Cancellation of Actual (LOR1) condition in the NSW region - 05/02/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 05/02/2025

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.124176 is cancelled at 1444 hrs 05/02/2025.

Manager NEM Real Time Operations
     
124176RESERVE NOTICE05/02/2025 02:04:22 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 05/02/2025

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 05/02/2025

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1330 hrs.
The Actual LOR1 condition is forecast to exist until 1430 hrs

The capacity reserve requirement is 1320 MW
The minimum capacity reserve available is 1254 MW

Manager NEM Real Time Operations
     
124137RESERVE NOTICE04/02/2025 07:50:28 PM

Cancellation of Actual (LOR1) condition in the NSW region - 04/02/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 04/02/2025

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.124131 is cancelled at 1930 hrs 04/02/2025.

Manager NEM Real Time Operations
     
124131RESERVE NOTICE04/02/2025 05:46:30 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 04/02/2025

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 04/02/2025

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1800 hrs

The capacity reserve requirement is 1370 MW
The minimum capacity reserve available is 1161 MW

Manager NEM Real Time Operations
     
124063GENERAL NOTICE04/02/2025 10:38:35 AM

NEM Local Temperature Alerts for SA, TAS, VIC from 04 Feb 2025 to 08 Feb 2025

AEMO ELECTRICITY MARKET NOTICE

AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.

SA
Port Augusta Ap (39+ Deg C): 6th Feb

TAS
Launceston Ti Tree Bend (33+ Deg C): 4th Feb

VIC
Latrobe Valley Ap (39+ Deg C): 4th Feb
Mildura Ap (39+ Deg C): 4th Feb, 6th Feb

The NEM Local Temperature Alert Levels are:

Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.

AEMO requests Market Participants to:

1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,

2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.

Further information is available at:

https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts

AEMO Operations Planning
     
124047CONSTRAINTS04/02/2025 09:32:40 AM

Update to system strength requirements in North Queensland

AEMO ELECTRICITY MARKET NOTICE

Refer to market notice 121468

AEMO and Powerlink are continuing to investigate system strength requirements in North Queensland.
The system normal equations have been revised to remove Gladstone >=1 requirement.

A revision to the constraint equations will be implemented at 1200 hrs on Tuesday 4th February 2025.

The new combinations have now published in a limits advice document on AEMO's website. For more information refer to the new limits advice: https://www.aemo.com.au/energy-systems/electricity/national-electricity-market-nem/system-operations/congestion-information-resource/limits-advice

This advice contains all the combinations for Queensland for system normal cases. Additional information has been included in the limit advice to clarify the requirement to disconnect all inverters/turbines under certain system conditions.

The constraint equation in the Q-NIL set of the form below will be modified:

-Q_NIL_STRGTH_xxxx
-Q_NIL_STRGTH_xxxx_I

AEMO Operations
     