STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 07/02/2025
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 124183 has been updated at 2133 hrs 05/02/2025 to the following:
From 1730 hrs 07/02/2025 to 1900 hrs 07/02/2025.
The forecast capacity reserve requirement is 1163 MW.
The minimum capacity reserve available is 1108 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
[EventId:202502051740_confirmed] Prices for interval 05-Feb-2025 17:40 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1800 hrs on 5 February 2025
PRICES ARE NOW CONFIRMED for trading interval 05-Feb-2025 17:40.
In accordance with Market Notice 124198 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202502051800_confirmed] Prices for interval 05-Feb-2025 18:00 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1800 hrs on 5 February 2025
PRICES ARE NOW CONFIRMED for trading interval 05-Feb-2025 18:00.
In accordance with Market Notice 124203 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202502051755_confirmed] Prices for interval 05-Feb-2025 17:55 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1800 hrs on 5 February 2025
PRICES ARE NOW CONFIRMED for trading interval 05-Feb-2025 17:55.
In accordance with Market Notice 124202 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202502051750_confirmed] Prices for interval 05-Feb-2025 17:50 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1800 hrs on 5 February 2025
PRICES ARE NOW CONFIRMED for trading interval 05-Feb-2025 17:50.
In accordance with Market Notice 124201 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202502051745_confirmed] Prices for interval 05-Feb-2025 17:45 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1800 hrs on 5 February 2025
PRICES ARE NOW CONFIRMED for trading interval 05-Feb-2025 17:45.
In accordance with Market Notice 124199 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202502051735_confirmed] Prices for interval 05-Feb-2025 17:35 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1800 hrs on 5 February 2025
PRICES ARE NOW CONFIRMED for trading interval 05-Feb-2025 17:35.
In accordance with Market Notice 124196 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 07/02/2025
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 124154 has been updated at 1500 hrs 05/02/2025 to the following:
From 1630 hrs to 1900 hrs 07/02/2025.
The forecast capacity reserve requirement is 1162 MW.
The minimum capacity reserve available is 842 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
Update - Vulnerable lines in TAS region
Update - Lightning vulnerable lines in TAS region
Refer to AEMO Electricity Market Notice 124044
At 1410 hrs 03/02/2025 the Farrell - Reece No.1 and No.2 220 kV lines lines tripped.
The cause of the trip was identified as due to lightning.
In accordance with SO_OP_3715, AEMO now considers the Farrell - Reece No.1 and No.2 220 kV lines to be vulnerable with a category of probable due to lightning.
Manager NEM Real Time Operations