Filter by category
Filter by Date
INC0139532 | Impact to Prudentials
SERVICE INTERRUPTION - ALERT
The service interruption relating to Prudentials & Settlements have now been resolved.
AEMO is working on the issue and will provide updates as more information becomes available.
For further enquiries please contact the AEMO Support Hub
Phone: 1300 236 600
Email: supporthub@aemo.com.au
AEMO IT Duty Manager
Inter-regional transfer limit variation - South East No.61 Capacitor 275kV - SA region - 20/12/2024
Inter-regional transfer limit variation - South East No.61 Capacitor 275kV - SA region - 20/12/2024
At 1445 hrs 20/12/2024 there was an unplanned outage of South East No.61 Capacitor 275kV.
The following constraint set(s) invoked at 1445 hrs 20/12/2024
S-SE_1CP
This constraint set(s) contains equations with the following interconnectors on the LHS.
V-SA
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Update Inter-regional transfer limit variation - Lismore SVC 132kV - NSW region - 20/12/2024
Inter-regional transfer limit variation - Lismore SVC 132kV - NSW region - 20/12/2024
At 1300 hrs 20/12/2024 there was a short notice outage of Lismore SVC 132kV.
The following constraint set(s) invoked at 1300 hrs 20/12/2024
N-LS_VC1
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - [outage element] - NSW region - 20/12/2024
Inter-regional transfer limit variation - [outage element] - NSW region - 20/12/2024
At 1300 hrs 20/12/2024 there was a short notice outage of [outage element].
The following constraint set(s) invoked at 1300 hrs 20/12/2024
N-LS_VC1
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
NEM Local Temperature Alerts for QLD from 20 Dec 2024 to 24 Dec 2024
AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.
QLD
Rockhampton Ap (39+ Deg C): 24th Dec
The NEM Local Temperature Alert Levels are:
Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.
AEMO requests Market Participants to:
1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,
2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.
Further information is available at:
https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts
AEMO Operations Planning
INC0139532 - ALERT - Impact to Prudentials
SERVICE INTERRUPTION - ALERT
AEMO is experiencing a service interruption relating to: Prudentials & Settlements.
AEMO is working on the issue and will provide updates as more information becomes available.
For further enquiries please contact the AEMO Support Hub
Phone: 1300 236 600
Email: supporthub@aemo.com.au
AEMO IT Duty Manager
Network Augmentation Commissioned - SA Region - 18/12/2024
Network Augmentation Commissioned - SA Region - 18/12/2024
At 0910 hrs 18/12/2024, the Para East Left Bus 275 kV Reactor has been commissioned.
Manager NEM Real Time Operations
Cancellation of the Actual Lack Of Reserve Level 1 (LOR1) condition in the NSW Region on 17/12/2024
The Actual LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 122113 is cancelled at 1745 hrs 17/12/2024.
Manager NEM Real Time Operations
Project Energy Connect (PEC-1) testing 18th December 2024 0700-2200 for flows in both directions up to 150 MW
Refer to market notice 120706
There is an opportunity for testing Project Energy Connect (PEC-1) for flows in both directions up to 150 MW on 18th December from 07:00hrs to 22:00hrs
This test includes switching of transmission lines and reactive plant in South Australia and in New South Wales.
Please also refer to the published formal PEC Stage 1 and HIC capacity release testing information at the following link https://aemo.com.au/-/media/files/stakeholder_consultation/consultations/nem-consultations/2023/project-energyconnect-stage-1-and-hic-capacity-release/pec-stage-1-and-hic---final-test-program.pdf?la=en.
Ben Blake
AEMO Operations