126467RESERVE NOTICE10/04/2025 11:52:24 AM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 10/04/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:


[1.] From 1800 hrs 10/04/2025 to 1830 hrs 10/04/2025.
The forecast capacity reserve requirement is 1595 MW.
The minimum capacity reserve available is 1577 MW.


Manager NEM Real Time Operations
     
126466GENERAL NOTICE10/04/2025 11:12:18 AM

Release of PEC-1 and combined V-SA limits - 11 April 2025

AEMO ELECTRICITY MARKET NOTICE

Refer to market notice 123956

AEMO, Transgrid and Electranet have reviewed the test results following the PEC Stage 1 testing on 31st January 2025. Hold points 4 and 5 can now be released.

The following limits will be released as of 1000hrs 11th April 2025:
- PEC-1 - 150 MW (both directions)
- Heywood + PEC1 - 750 MW from Vic to SA and 700 MW from SA to Vic
- The existing Heywood limits of 600 and 550 MW are not being changed.

With the release of these limits AEMO will be looking for testing opportunities for increases to Heywood as per the test plan: https://aemo.com.au/-/media/files/stakeholder_consultation/consultations/nem-consultations/2023/project-energyconnect-stage-1-and-hic-capacity-release/pec-stage-1-and-hic---final-test-program.pdf?la=en.

Ben Blake
AEMO Operations
     
126465INTER-REGIONAL TRANSFER10/04/2025 10:00:31 AM

Update - Inter-regional transfer limit variation - APD - Heywood - Mortlake 500 kV line - VIC region - 10/04/2025

AEMO ELECTRICITY MARKET NOTICE

Update - Inter-regional transfer limit variation - APD - Heywood - Mortlake 500 kV line - VIC region - 10/04/2025

Refer to Market Notice 126464.

The cause of the unplanned outage of APD - Heywood - Mortlake 500 kV line in the VIC region has been identified and resolved. The outage has been completed and the APD - Heywood - Mortlake 500 kV line returned to service at 0948 hrs 10/04/2025

Constraint set(s) revoked: V-HYMO

Manager NEM Real Time Operations
     
126464INTER-REGIONAL TRANSFER10/04/2025 08:49:30 AM

Inter-regional transfer limit variation - APD - Heywood - Mortlake 500 kV line - VIC region - 10/04/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - APD - Heywood - Mortlake 500 kV line - VIC region - 10/04/2025

At 0825 hrs 10/04/2025 there was an unplanned outage of the APD - Heywood - Mortlake 500 kV line.

The following constraint set(s) invoked at 0835 hrs 10/04/2025
V-HYMO

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-SA,T-V-MNSP1,V-S-MNSP1,VIC1-NSW1,NSW1-QLD1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
126444RESERVE NOTICE09/04/2025 04:43:48 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 09/04/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:


[1.] From 1730 hrs 09/04/2025 to 1800 hrs 09/04/2025.
The forecast capacity reserve requirement is 1519 MW.
The minimum capacity reserve available is 1500 MW.


Manager NEM Real Time Operations
     
126443RESERVE NOTICE09/04/2025 02:47:55 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 10/04/2025.

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 126441 is cancelled at 1440 hrs 09/04/2025.

Manager NEM Real Time Operations
     
126441RESERVE NOTICE09/04/2025 02:18:08 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 10/04/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:


[1.] From 1800 hrs 10/04/2025 to 1830 hrs 10/04/2025.
The forecast capacity reserve requirement is 1581 MW.
The minimum capacity reserve available is 1580 MW.


Manager NEM Real Time Operations
     
126263GENERAL NOTICE04/04/2025 08:11:29 AM

Update - Vulnerable lines in Qld region

AEMO ELECTRICITY MARKET NOTICE.

Update - Lightning vulnerable lines in Qld region
Refer to AEMO Electricity Market Notice 126262 and 126271
At 0152 hrs 04/04/2025 the the Ross - Townsville South No 7156 and 7249 132kV lines tripped.
The cause of the trip was identified as due to lightning.
In accordance with SO_OP_3715, AEMO now considers the the Ross - Townsville South No 7156 and 7249 132kV lines to be vulnerable with a category of probable due to lightning.

Manager NEM Real Time Operations
     
126058INTER-REGIONAL TRANSFER30/03/2025 02:14:22 PM

Inter-regional transfer limit variation - constraint automation to manage Power System Security in NSW region - 30/03/2025

AEMO ELECTRICITY MARKET NOTICE

In order to maintain the power system in a secure operating state in the NSW region, AEMO has invoked automated constraint set CA_SYDS_56FB4FDD from 1405 hrs until further notice.

This constraint set contains equations with the following interconnector on the LHS;

VIC1-NSW1

Refer to AEMO Network Outage Scheduler (NOS) for further information.

Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm