122983MARKET INTERVENTION09/01/2025 09:10:02 AM

Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT

Refer to Market Notice 122981

Direction is cancelled from: 0910 hrs 09/01/2025

Manager NEM Real Time Operations
     
122981MARKET INTERVENTION08/01/2025 04:01:50 PM

Direction - SA region to Pelican Point Power Limited - PPCCGT PELICAN POINT

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region to Pelican Point Power Limited - PPCCGT PELICAN POINT

Refer to Market Notice 122980


In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to Pelican Point Power Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT at 1600 hrs 08/01/2025
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 0930 hrs 09/01/2025
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: The synchronous generating units currently expected to be synchronised in SA will be inadequate to maintain sufficient Voltage Control in SA. Intervention is required to maintain the power system in a secure operating state
Expected duration: 1500 hrs 09/01/2025 / further notice.

Pelican Point Power Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     
122980MARKET INTERVENTION08/01/2025 03:59:58 PM

Direction - SA region 08/01/2025

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region 08/01/2025

In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1605 hrs on 08/01/2025.

Intervention pricing does not apply to this AEMO intervention event.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.


Manager NEM Real Time Operations
     
122978MARKET INTERVENTION08/01/2025 03:01:27 PM

Cancellation - AEMO Intervention Event - SA region 07/01/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - SA region 07/01/2025

Refer to Market Notice 122948

The AEMO Intervention Event and all associated directions are cancelled from 1500 hrs on 08/01/2025.


Manager NEM Real Time Operations
     
122977MARKET INTERVENTION08/01/2025 03:00:03 PM

Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT

Refer to Market Notice 122957

Direction is cancelled from: 1500 hrs 08/01/2025

Manager NEM Real Time Operations
     
122976MARKET INTERVENTION08/01/2025 02:08:25 PM

Foreseeable AEMO intervention in SA region

AEMO ELECTRICITY MARKET NOTICE

Foreseeable AEMO intervention in SA region

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0930 hrs 09/01/2025.

The foreseeable circumstance requiring the need for intervention is Voltage.

AEMO estimates that, in the absence of sufficient market response by 1600 hrs 08/01/2025, AEMO may need to intervene by issuing a direction.

Manager NEM Real Time Operations
     
122963SETTLEMENTS RESIDUE08/01/2025 01:31:54 PM

[EventId:202501081330_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 08 January 2025 13:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1330 hrs on 8 January 2025

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 8 January 2025.

Refer to market notice: 122960

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1330 hrs on 8 January 2025.

This is an AEMO autogenerated Market Notice.
     
122962INTER-REGIONAL TRANSFER08/01/2025 12:20:09 PM

Inter-regional transfer limit variation - Hummocks - Bungama - Snowtown 132kV Line - SA region - 08/01/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Hummocks - Bungama - Snowtown 132kV Line - SA region - 08/01/2025

At 1210 hrs 08/01/2025 there was a short notice outage of Hummocks - Bungama - Snowtown 132kV Line.

The following constraint set(s) invoked at 1210 hrs 08/01/2025
S-HUBG

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
122961INTER-REGIONAL TRANSFER08/01/2025 12:09:21 PM

Inter-regional transfer limit variation - constraint automation to manage Power System Security in NSW region - 08/01/2025

AEMO ELECTRICITY MARKET NOTICE

In order to maintain the power system in a secure operating state in the NSW region, AEMO has invoked automated constraint set CA_BRIS_56906542 from 1155 hrs until further notice.

This constraint set contains equations with the following interconnector on the LHS;

V-S-MNSP1
VIC1-NSW1

Manager NEM Real Time Operations
     