123529MARKET INTERVENTION21/01/2025 04:00:12 PM

Direction - SA region to Pelican Point Power Limited - PPCCGT PELICAN POINT

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region to Pelican Point Power Limited - PPCCGT PELICAN POINT

Refer to Market Notice 123506


In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to Pelican Point Power Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT at 1600 hrs 21/01/2025
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 2230 hrs 21/01/2025
Services provided: Voltage Control
Circumstances necessitating the Direction:Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 0400 hrs 23/01/2025 / further notice.

Pelican Point Power Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     
123528MARKET INTERVENTION21/01/2025 04:07:18 PM

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 123504

TORRB3 TORRENS ISLAN at 0800 hrs 21/01/2025 to Remain synchronised and follow dispatch targets.

The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 23/01/2025.

The direction update is issued at 1605 hrs 21/01/2025.

Manager NEM Real Time Operations
     
123527MARKET INTERVENTION21/01/2025 03:58:37 PM

Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT

Refer to Market Notice 123505

Direction is cancelled from: 1630 hrs 21/01/2025

Manager NEM Real Time Operations
     
123521NON-CONFORMANCE21/01/2025 01:55:12 PM

NON-CONFORMANCE Region QLD1 Tuesday, 21 January 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Tuesday, 21 January 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_1
Duration: 21/01/2025 09:45 to 21/01/2025 13:55
Amount: 36 MW
Constraint: NC-Q_MPP_1

Auto-generated on behalf of Manager NEM Real Time Operations
     
123517GENERAL NOTICE21/01/2025 01:23:56 PM

Network Augmentation Commissioned - NSW Region - 21/01/2025

AEMO ELECTRICITY MARKET NOTICE

Refer Market notice: 123507

Network Augmentation Commissioned - NSW Region - 21/01/2025

Commissioned: Bundey to Buronga 330 kV (6F) line.
Buronga No. 5 330 kV/330 kV phase shifting transformer

Manager NEM Real Time Operations
     
123516GENERAL NOTICE21/01/2025 12:13:17 PM

Update - Pre dispatch demand forecast error - NEM regions

AEMO ELECTRICITY MARKET NOTICE

Update - Pre dispatch demand forecast error - NEM regions

Refer market notice: 123513

The issue relating to the Pre dispatch demand forecast error has been resolved.

Manager NEM Real Time Operations
     
123514GENERAL NOTICE21/01/2025 11:23:21 AM

NEM Local Temperature Alerts for QLD, VIC from 21 Jan 2025 to 25 Jan 2025

AEMO ELECTRICITY MARKET NOTICE

AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.

QLD
Dalby Ap (37+ Deg C): 22nd Jan, 23rd Jan, 24th Jan
Rockhampton Ap (39+ Deg C): 23rd Jan

VIC
Mildura Ap (39+ Deg C): 21st Jan

The NEM Local Temperature Alert Levels are:

Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.

AEMO requests Market Participants to:

1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,

2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.

Further information is available at:

https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts

AEMO Operations Planning
     
123513GENERAL NOTICE21/01/2025 10:20:37 AM

Pre dispatch demand forecast error - NEM regions

AEMO ELECTRICITY MARKET NOTICE

Pre dispatch demand forecast error - NEM regions

AEMO is aware of an error in the Pre dispatch demand forecast for the NEM regions
AEMO is currently working to resolve the issue.
Dispatch results are not impacted.


Manager NEM Real Time Operations
     
123507GENERAL NOTICE20/01/2025 04:53:28 PM

Bundey to Buronga (6F) line to be energised 0700 21st January 2025

AEMO ELECTRICITY MARKET NOTICE

Refer to market notice 122115

The Bundey to Buronga 330kV (6F) line will be energised at 0700 hrs 21st January 2025. This is to facilitate further testing of PEC-1. Any future outages of 6F will be notified via NOS.

When further testing of PEC-1 opportunities arise these will be notified via market notice. At this time there are no opportunities for testing forecast.

Please also refer to the published formal PEC Stage 1 and HIC capacity release testing information at the following link https://aemo.com.au/-/media/files/stakeholder_consultation/consultations/nem-consultations/2023/project-energyconnect-stage-1-and-hic-capacity-release/pec-stage-1-and-hic---final-test-program.pdf?la=en.

Ben Blake
AEMO Operations
     