Inter-regional transfer limit variation - Greenbank 275kV SVC - QLD region - 13/02/2025
Inter-regional transfer limit variation - Greenbank 275kV SVC - QLD region - 13/02/2025
At 1738 hrs 13/02/2025 there was an unplanned outage of the Greenbank 275kV SVC.
The following constraint set(s) invoked at 1745 hrs 13/02/2025
Q-GB_VC
This constraint set(s) contains equations with the following interconnectors on the LHS.
NSW1-QLD1,N-Q-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Directlink- NSW region - 13/02/2025
Inter-regional transfer limit variation - No.2 Leg of Directlink - NSW region - 13/02/2025
A planned outage of the No.2 Leg of Directlink in the NSW region was scheduled from 1517 hrs 30/01/2025 to 1700 hrs 20/02/2025.
The outage has been completed and the No.2 Leg of Directlink returned to service at 1312 hrs 13/02/2025
Constraint set(s) revoked: N-X_MBTE_2
Manager NEM Real Time Operations
Fast Frequency Response Market - Removal of R1 FCAS dispatch cap from 17th February 2025
Following review of the operation of the Very Fast FCAS market, from 1300 hrs AEST on Monday 17th February AEMO will remove the cap on dispatch of Very Fast Raise (R1) Contingency FCAS.
No other changes to the dispatch of Very Fast FCAS or FCAS constraint equations will be made on this date.
For information on the Fast Frequency Response (FFR) initiative please visit the website at: https://www.aemo.com.au/initiatives/major-programs/fast-frequency-response
Andrew Groom
AEMO Operations
PDPASA - Update of the suspect Lack Of Reserve Level 2 (LOR2) condition in the QLD Region on 13/02/2025
The suspect LOR2 condition advised in AEMO Electricity Market Notice No. 124585 has been reviewed.
AEMO considers this forecast LOR2 condition invalid
No LOR2 condition is currently forecast for the QLD region.
Manager NEM Real Time Operation
PDPASA - Suspect Lack Of Reserve Level 2 (LOR2) in the QLD Region on 13/02/2025
AEMO considers that there is a suspect Forecast LOR2 condition for the QLD region for the following period[s]:
[1.] From 1830 hrs 13/02/2025 to 1930 hrs 13/02/2025.
The forecast capacity reserve requirement is 639 MW.
The minimum capacity reserve available is 480 MW.
AEMO is currently investigating this LOR2 forecast condition to confirm whether they are valid.
Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the SA region - 12/02/2025
Cancellation of Actual (LOR1) condition in the SA region - 12/02/2025
The Actual LOR1 Condition in the SA Region advised in AEMO Electricity Market Notice No.124572 is cancelled at 2040 hrs 12/02/2025.
Manager NEM Real Time Operations
Cancellation of Actual (LOR2) condition in the SA region - 12/02/2025
Cancellation of Actual (LOR2) condition in the SA region - 12/02/2025
The Actual LOR2 Condition in the SA Region advised in AEMO Electricity Market Notice No.124573 is cancelled at 1940 hrs 12/02/2025.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 2 (LOR2) in the SA region - 12/02/2025
Actual Lack Of Reserve Level 2 (LOR2) in the SA region - 12/02/2025
An Actual LOR2 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the SA region from 1900 hrs.
The Actual LOR2 condition is forecast to exist until 1930 hrs
The capacity reserve required is 245 MW
The minimum reserve available is 107 MW
AEMO is seeking an immediate market response.
An insufficient market response may require AEMO to implement a AEMO intervention event.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 12/02/2025
Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 12/02/2025
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the SA region from 1830 hrs.
The Actual LOR1 condition is forecast to exist until 1930 hrs
The capacity reserve requirement is 524 MW
The minimum capacity reserve available is 470 MW
Manager NEM Real Time Operations