124034RESERVE NOTICE03/02/2025 04:54:30 AM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 03/02/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 124026 has been updated at 0445 hrs 03/02/2025 to the following:

[1.] From 1800 hrs 03/02/2025 to 1830 hrs 03/02/2025.
The forecast capacity reserve requirement is 598 MW.
The minimum capacity reserve available is 419 MW.

[2.] From 1930 hrs 03/02/2025 to 2030 hrs 03/02/2025.
The forecast capacity reserve requirement is 617 MW.
The minimum capacity reserve available is 380 MW.


Manager NEM Real Time Operations
     
124026RESERVE NOTICE03/02/2025 12:03:05 AM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 03/02/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following Period:


[1.] From 1800 hrs 03/02/2025 to 2000 hrs 03/02/2025.
The forecast capacity reserve requirement is 630 MW.
The minimum capacity reserve available is 384 MW.


Manager NEM Real Time Operations
     
124025RESERVE NOTICE03/02/2025 12:09:13 AM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the VIC Region on 03/02/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the VIC region for the following Period:


[1.] From 1800 hrs 03/02/2025 to 1930 hrs 03/02/2025.
The forecast capacity reserve requirement is 1135 MW.
The minimum capacity reserve available is 999 MW.


Manager NEM Real Time Operations
     
124020INTER-REGIONAL TRANSFER02/02/2025 10:38:53 PM

Update - Inter-regional transfer limit variation - Ararat to Waubra to Ballarat 220 kV line - VIC region - 02/02/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Ararat to Waubra to Ballarat 220 kV line - VIC region - 02/02/2025

At 2138 hrs 02/02/2025 there was an unplanned outage of Ararat to Waubra to Ballarat 220 kV line.

The following constraint set(s) invoked at 2150 hrs 02/02/2025
V-AR_WB_BA

The following constraint set(s) invoked at 2230 hrs 02/02/2025
V-KIAMAL_SC_220CB

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1,T-V-MNSP1,V-SA,VIC1-NSW1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
124017INTER-REGIONAL TRANSFER02/02/2025 10:04:02 PM

Inter-regional transfer limit variation - Ararat to Waubra to Ballarat 220 kV line - VIC region - 02/02/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Ararat to Waubra to Ballarat 220 kV line - VIC region - 02/02/2025

At 2138 hrs 02/02/2025 there was an unplanned outage of Ararat to Waubra to Ballarat 220 kV line.

The following constraint set(s) invoked at 2150 hrs 02/02/2025
V-AR_WB_BA

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1,T-V-MNSP1,V-SA,VIC1-NSW1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
124000RESERVE NOTICE02/02/2025 02:39:02 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 07/02/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period[s]:

[1.] From 1600 hrs 07/02/2025 to 1800 hrs 07/02/2025.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1160 MW.

Manager NEM Real Time Operations
     
123999MARKET INTERVENTION02/02/2025 09:08:43 AM

Cancellation - AEMO Intervention Event - SA region 01/02/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - SA region 01/02/2025

Refer to Market Notice 123988

The AEMO Intervention Event and all associated directions are cancelled from 0900 hrs on 02/02/2025.


Manager NEM Real Time Operations
     
123998MARKET INTERVENTION02/02/2025 09:02:34 AM

Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT

Refer to Market Notice 123989

Direction is cancelled from: 0900 hrs 02/02/2025

Manager NEM Real Time Operations
     
123995SETTLEMENTS RESIDUE01/02/2025 06:30:45 PM

[EventId:202502011830_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 01 February 2025 18:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1830 hrs on 1 February 2025

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 1 February 2025.

Refer to market notice: 123990

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.

The negative residue constraint NRM_VIC1_SA1 ceased operating at 1830 hrs on 1 February 2025.

This is an AEMO autogenerated Market Notice.
     