125666MARKET INTERVENTION15/03/2025 02:17:06 PM

Update - Foreseeable AEMO intervention in SA region

AEMO ELECTRICITY MARKET NOTICE

Update - Foreseeable AEMO intervention in SA region

Refer AEMO Electricity Market Notice 125664

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0130 hrs 16/03/2025.

The foreseeable circumstance requiring the need for intervention is Voltage.

AEMO estimates that, in the absence of sufficient market response by 1600 hrs 15/03/2025, AEMO may need to intervene by issuing a direction.

Manager NEM Real Time Operations
     
125664MARKET INTERVENTION15/03/2025 01:25:17 PM

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO ELECTRICITY MARKET NOTICE

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0130 hrs 16/03/2025.

The foreseeable circumstance requiring the need for intervention is Voltage.

Manager NEM Real Time Operations
     
125647INTER-REGIONAL TRANSFER14/03/2025 05:11:12 PM

Inter-regional transfer limit variation - Lennox Head - Suffolk Park 9G3 132 kV Line - NSW region - 14/03/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Lennox Head - Suffolk Park 9G3 132 kV Line - NSW region - 14/03/2025

At 1647 hrs 14/03/2025 there was a short notice outage of Lennox Head - Suffolk Park 9G3 132 kV Line.

The following constraint set(s) invoked at 1700 hrs 14/03/2025
N-BAMB_132_OPEN

This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
125621INTER-REGIONAL TRANSFER14/03/2025 06:03:13 AM

Inter-regional transfer limit variation - Hummocks - Waterloo 132 kV line - SA region - 14/03/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Hummocks - Waterloo 132 kV line - SA region - 14/03/2025

At 0457 hrs 14/03/2025 there was an unplanned outage of Hummocks - Waterloo 132 kV line.

The following constraint set(s) invoked at 0505 hrs 14/03/2025
S-HUWT

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
125620INTER-REGIONAL TRANSFER14/03/2025 06:03:11 AM

Inter-regional transfer limit variation - Hummocks - Bungama 132 kV line - SA region - 14/03/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Hummocks - Bungama 132 kV line - SA region - 14/03/2025

At 0457 hrs 14/03/2025 there was an unplanned outage of Hummocks - Bungama 132 kV line.

The following constraint set(s) invoked at 0505 hrs 14/03/2025
S-HUBG

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1,V-SA

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
125560INTER-REGIONAL TRANSFER12/03/2025 02:20:15 PM

Inter-regional transfer limit variation - Directlink Cables 1 and 2 - NSW region - 12/03/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Directlink Cables 1 and 2 - NSW region - 12/03/2025

An unplanned outage of Directlink Cables 1 and 2 in the NSW region was scheduled to return to service at 1700 hrs 12/03/2025.

The outage has been completed and Directlink Cables 1 and 2 returned to service at 1350 hrs 12/03/2025

Constraint set(s) revoked: N-X_MBTE_3

Manager NEM Real Time Operations
     
125543INTER-REGIONAL TRANSFER12/03/2025 07:03:39 AM

Inter-regional transfer limit variation - Waterloo - Hummocks 132kV Line - SA region - 12/03/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Waterloo - Hummocks 132kV Line - SA region - 12/03/2025

At 0641 hrs 12/03/2025 there was an unplanned outage of Waterloo - Hummocks 132kV Line.

The following constraint set(s) invoked at 0650 hrs 12/03/2025
S-HUWT

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
125518INTER-REGIONAL TRANSFER11/03/2025 10:05:53 AM

Inter-regional transfer limit variation - Penola West - South East 132 kV line and Kincraig - Penola West 132 kV line - SA region - 11/03/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Penola West - South East 132 kV line and Kincraig - Penola West 132 kV line - SA region - 11/03/2025

At 0917 hrs 11/03/2025 there was an unplanned outage of Penola West - South East 132 kV line and Kincraig - Penola West 132 kV line.

The following constraint set(s) invoked at 0925 hrs 11/03/2025
S-KNPW and S-PWSE.

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-SA

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
125431MARKET INTERVENTION09/03/2025 01:27:46 PM

Cancellation - AEMO Intervention Event - SA region 08/03/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - SA region 08/03/2025

Refer to Market Notice 125396

The AEMO Intervention Event and all associated directions are cancelled from 1330 hrs on 09/03/2025.


Manager NEM Real Time Operations
     