Project Energy Connect (PEC-1) testing 25th January 2025 0100-0300 for flows from Victoria to South Australia direction up to 150 MW
Refer to market notice 122115
There is an opportunity for testing Project Energy Connect (PEC-1) for flows from Victoria to South Australia direction up to 150 MW on 25th January from 01:00hrs to 03:00hrs
This test includes switching of transmission lines and reactive plant in South Australia and in New South Wales.
Please also refer to the published formal PEC Stage 1 and HIC capacity release testing information at the following link https://aemo.com.au/-/media/files/stakeholder_consultation/consultations/nem-consultations/2023/project-energyconnect-stage-1-and-hic-capacity-release/pec-stage-1-and-hic---final-test-program.pdf?la=en.
Ben Blake
AEMO Operations
[EventId:202501241410_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 24 January 2025 14:10
Issued by Australian Energy Market Operator Ltd at 1410 hrs on 24 January 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 24 January 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1410 hrs on 24 January 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202501241300_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 24 January 2025 13:00
Issued by Australian Energy Market Operator Ltd at 1300 hrs on 24 January 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 24 January 2025.
Refer to market notice: 123665
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1300 hrs on 24 January 2025.
This is an AEMO autogenerated Market Notice.
[EventId:202501241200_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 24 January 2025 12:00
Issued by Australian Energy Market Operator Ltd at 1200 hrs on 24 January 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 24 January 2025.
Refer to market notice: 123654
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.
The negative residue constraint NRM_VIC1_SA1 ceased operating at 1200 hrs on 24 January 2025.
This is an AEMO autogenerated Market Notice.
[EventId:202501241135_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 24 January 2025 11:35
Issued by Australian Energy Market Operator Ltd at 1135 hrs on 24 January 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 24 January 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1135 hrs on 24 January 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202501241110_confirmed] Prices for interval 24-Jan-2025 11:10 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1130 hrs on 24 January 2025
PRICES ARE NOW CONFIRMED for trading interval 24-Jan-2025 11:10.
In accordance with Market Notice 123653 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202501241130_confirmed] Prices for interval 24-Jan-2025 11:30 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1130 hrs on 24 January 2025
PRICES ARE NOW CONFIRMED for trading interval 24-Jan-2025 11:30.
In accordance with Market Notice 123658 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202501241125_confirmed] Prices for interval 24-Jan-2025 11:25 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1130 hrs on 24 January 2025
PRICES ARE NOW CONFIRMED for trading interval 24-Jan-2025 11:25.
In accordance with Market Notice 123657 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202501241120_confirmed] Prices for interval 24-Jan-2025 11:20 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1130 hrs on 24 January 2025
PRICES ARE NOW CONFIRMED for trading interval 24-Jan-2025 11:20.
In accordance with Market Notice 123656 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.