Update - Non-credible contingency event - NSW region - 21/02/2025
Update - Non-credible contingency event - NSW region - 21/02/2025
Refer AEMO Electricity Market Notice 124944
At 1030 hrs the Capital WF A and C 330kV Buses were returned to service.
The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.
AEMO will not reclassify this event as a credible contingency event.
Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Friday, 21 February 2025
NON-CONFORMANCE QLD1 Region Friday, 21 February 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: GANGARR1
Duration: 21/02/2025 09:40 to 21/02/2025 10:20
Amount: 72 MW
Constraint: NC-Q_GANGARR1
Auto-generated on behalf of Manager NEM Real Time Operations
NEM Local Temperature Alerts for SA, VIC from 21 Feb 2025 to 25 Feb 2025
AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.
SA
Mt Gambier Ap (39+ Deg C): 22nd Feb
Port Augusta Ap (39+ Deg C): 22nd Feb, 25th Feb
VIC
Mildura Ap (39+ Deg C): 22nd Feb
Mortlake (39+ Deg C): 22nd Feb
The NEM Local Temperature Alert Levels are:
Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.
AEMO requests Market Participants to:
1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,
2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.
Further information is available at:
https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts
AEMO Operations Planning
Non-credible contingency event - NSW region - 20/02/2025
Non-credible contingency event - NSW region - 20/02/2025
At 1619 hrs the Capital WF A and C 330kV Buses tripped.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Thursday, 20 February 2025
NON-CONFORMANCE NSW1 Region Thursday, 20 February 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: CAPBES1
Duration: 20/02/2025 14:15 to 20/02/2025 14:25
Amount: 70 MW
Constraint: NC-N_CAPBES1
Auto-generated on behalf of Manager NEM Real Time Operations
NEM Local Temperature Alerts for SA, VIC from 20 Feb 2025 to 24 Feb 2025
AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.
SA
Adelaide West Terrace (39+ Deg C): 22nd Feb
Clare High School (39+ Deg C): 22nd Feb
Mt Gambier Ap (39+ Deg C): 22nd Feb
Port Augusta Ap (39+ Deg C): 22nd Feb
VIC
Mildura Ap (39+ Deg C): 22nd Feb
Mortlake (39+ Deg C): 22nd Feb
The NEM Local Temperature Alert Levels are:
Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.
AEMO requests Market Participants to:
1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,
2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.
Further information is available at:
https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts
AEMO Operations Planning
NON-CONFORMANCE Region SA1 Thursday, 20 February 2025
NON-CONFORMANCE SA1 Region Wednesday, 19 February 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: CLEMGPWF
Duration: 19/02/2025 17:30 to 20/02/2025 07:55
Amount: 15 MW
Constraint: NC-S_CLEMGPWF
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Thursday, 20 February 2025
NON-CONFORMANCE NSW1 Region Thursday, 20 February 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: WTAHB1
Duration: 20/02/2025 03:30 to 20/02/2025 03:45
Amount: -8 MW
Constraint: NC-N_WTAHB1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Thursday, 20 February 2025
NON-CONFORMANCE NSW1 Region Thursday, 20 February 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: WTAHB1
Duration: 20/02/2025 02:20 to 20/02/2025 03:00
Amount: -9 MW
Constraint: NC-N_WTAHB1
Auto-generated on behalf of Manager NEM Real Time Operations