Filter by category
Filter by Date
[EventId:202412301600_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 30 December 2024 16:00
Issued by Australian Energy Market Operator Ltd at 1600 hrs on 30 December 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 30 December 2024.
Refer to market notice: 122589
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1600 hrs on 30 December 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202412301435_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 30 December 2024 14:35
Issued by Australian Energy Market Operator Ltd at 1435 hrs on 30 December 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 30 December 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1435 hrs on 30 December 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202412301330_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 30 December 2024 13:30
Issued by Australian Energy Market Operator Ltd at 1330 hrs on 30 December 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 30 December 2024.
Refer to market notice: 122579
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1330 hrs on 30 December 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202412301020_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 30 December 2024 10:20
Issued by Australian Energy Market Operator Ltd at 1020 hrs on 30 December 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 30 December 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1020 hrs on 30 December 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
NON-CONFORMANCE Region NSW1 Sunday, 29 December 2024
NON-CONFORMANCE NSW1 Region Saturday, 28 December 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: WLWLSF1
Duration: 28/12/2024 11:40 to 29/12/2024 08:45
Amount: 147 MW
Constraint: NC-N_WLWLSF1
Auto-generated on behalf of Manager NEM Real Time Operations
[EventId:202412271905_NRM_QLD1_NSW1_stopped] NEGRES CONSTRAINT NRM_QLD1_NSW1 ceased operating from 27 December 2024 19:05
Issued by Australian Energy Market Operator Ltd at 1905 hrs on 27 December 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 27 December 2024.
Refer to market notice: 122533
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the QLD to NSW directional interconnector.
The negative residue constraint NRM_QLD1_NSW1 ceased operating at 1905 hrs on 27 December 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202412271830_NRM_QLD1_NSW1_started] NEGRES CONSTRAINT NRM_QLD1_NSW1 started operating from 27 December 2024 18:30
Issued by Australian Energy Market Operator Ltd at 1830 hrs on 27 December 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 27 December 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the QLD to NSW directional interconnector.
The negative residue constraint set NRM_QLD1_NSW1 commenced operating from 1830 hrs on 27 December 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
N-Q-MNSP1
NSW1-QLD1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202412271510_confirmed] Prices for interval 27-Dec-2024 15:10 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1530 hrs on 27 December 2024
PRICES ARE NOW CONFIRMED for trading interval 27-Dec-2024 15:10.
In accordance with Market Notice 122518 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202412271530_confirmed] Prices for interval 27-Dec-2024 15:30 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1530 hrs on 27 December 2024
PRICES ARE NOW CONFIRMED for trading interval 27-Dec-2024 15:30.
In accordance with Market Notice 122522 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.