Filter by category
Filter by Date
INC0139532 | Impact to Prudentials
SERVICE INTERRUPTION - ALERT
The service interruption relating to Prudentials & Settlements have now been resolved.
AEMO is working on the issue and will provide updates as more information becomes available.
For further enquiries please contact the AEMO Support Hub
Phone: 1300 236 600
Email: supporthub@aemo.com.au
AEMO IT Duty Manager
Inter-regional transfer limit variation - South East No.61 Capacitor 275kV - SA region - 20/12/2024
Inter-regional transfer limit variation - South East No.61 Capacitor 275kV - SA region - 20/12/2024
At 1445 hrs 20/12/2024 there was an unplanned outage of South East No.61 Capacitor 275kV.
The following constraint set(s) invoked at 1445 hrs 20/12/2024
S-SE_1CP
This constraint set(s) contains equations with the following interconnectors on the LHS.
V-SA
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Update Inter-regional transfer limit variation - Lismore SVC 132kV - NSW region - 20/12/2024
Inter-regional transfer limit variation - Lismore SVC 132kV - NSW region - 20/12/2024
At 1300 hrs 20/12/2024 there was a short notice outage of Lismore SVC 132kV.
The following constraint set(s) invoked at 1300 hrs 20/12/2024
N-LS_VC1
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - [outage element] - NSW region - 20/12/2024
Inter-regional transfer limit variation - [outage element] - NSW region - 20/12/2024
At 1300 hrs 20/12/2024 there was a short notice outage of [outage element].
The following constraint set(s) invoked at 1300 hrs 20/12/2024
N-LS_VC1
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
INC0139532 - ALERT - Impact to Prudentials
SERVICE INTERRUPTION - ALERT
AEMO is experiencing a service interruption relating to: Prudentials & Settlements.
AEMO is working on the issue and will provide updates as more information becomes available.
For further enquiries please contact the AEMO Support Hub
Phone: 1300 236 600
Email: supporthub@aemo.com.au
AEMO IT Duty Manager
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 17/12/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 122118 is cancelled at 1920 hrs 17/12/2024.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 17/12/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
[1.] From 1830 hrs 17/12/2024 to 1900 hrs 17/12/2024.
The forecast capacity reserve requirement is 1662 MW.
The minimum capacity reserve available is 1551 MW.
Manager NEM Real Time Operations
Cancellation of the Actual Lack Of Reserve Level 1 (LOR1) condition in the NSW Region on 17/12/2024
The Actual LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 122113 is cancelled at 1745 hrs 17/12/2024.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 17/12/2024
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 17/12/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1530 hrs.
The Actual LOR1 condition is forecast to exist until 1800 hrs
The capacity reserve requirement is 1340 MW
The minimum capacity reserve available is 1082 MW
Manager NEM Real Time Operations