Filter by category
Filter by Date
Direction - SA region to AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Direction - SA region to AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer to Market Notice 122279
In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN at 1445 hrs 20/12/2024
Type of resource: generating unit
Required actions: Synchronise and follow dispatch targets at 0400 hrs 21/12/2024
Services provided: Voltage Control
Circumstances necessitating the Direction:Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 0400 hrs 22/12/2024 / further notice.
AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer to Market Notice 122277
The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 22/12/2024.
The direction update is issued at 1445 hrs 20/12/2024.
Manager NEM Real Time Operations
[EventId:202412201235_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 20 December 2024 12:35
Issued by Australian Energy Market Operator Ltd at 1235 hrs on 20 December 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 20 December 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1235 hrs on 20 December 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
Cancellation of Forecast Minimum System Load MSL2 event in the VIC Region on 22/12/2024
Cancellation - Forecast MSL2 - VIC Region at 1200 hrs 20/12/2024.
Refer to Market Notice 122305 for MSL2.
AEMO Operations
[EventId:202412201130_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 20 December 2024 11:30
Issued by Australian Energy Market Operator Ltd at 1130 hrs on 20 December 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 20 December 2024.
Refer to market notice: 122304
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1130 hrs on 20 December 2024.
This is an AEMO autogenerated Market Notice.
Forecast Minimum System Load (MSL2) condition in the VIC region on 22/12/2024
AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC region on 22/12/2024.
Minimum System Load (MSL) conditions are forecast when regional demand is less than the relevant MSL threshold. The advisory MSL thresholds are:
o MSL1 - 1825 MW
o MSL2 - 1325 MW
o MSL3 - 825 MW
The regional demand is forecast to be below the MSL2 threshold for the following period:
From 1230 hrs 22/12/2024 to 1300 hrs 22/12/2024. Minimum regional demand is forecast to be 1284 MW at 1300 hrs.
Forecast regional demand (DEMAND50) is published in Short Term and Pre-Dispatch PASA region solution reports available on Market Data NEMWEB: https://aemo.com.au/en/energy-systems/electricity/national-electricity-market-nem/data-nem/market-data-nemweb .
AEMO Operations
[EventId:202412200805_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 20 December 2024 08:05
Issued by Australian Energy Market Operator Ltd at 0805 hrs on 20 December 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 20 December 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 0805 hrs on 20 December 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202412200710_confirmed] Prices for interval 20-Dec-2024 07:10 are now confirmed
Issued by Australian Energy Market Operator Ltd at 0730 hrs on 20 December 2024
PRICES ARE NOW CONFIRMED for trading interval 20-Dec-2024 07:10.
In accordance with Market Notice 122292 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202412200730_confirmed] Prices for interval 20-Dec-2024 07:30 are now confirmed
Issued by Australian Energy Market Operator Ltd at 0730 hrs on 20 December 2024
PRICES ARE NOW CONFIRMED for trading interval 20-Dec-2024 07:30.
In accordance with Market Notice 122296 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.