[EventId:202501071305_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 07 January 2025 13:05
Issued by Australian Energy Market Operator Ltd at 1305 hrs on 7 January 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 7 January 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1305 hrs on 7 January 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202501071230_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 07 January 2025 12:30
Issued by Australian Energy Market Operator Ltd at 1230 hrs on 7 January 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 7 January 2025.
Refer to market notice: 122931
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1230 hrs on 7 January 2025.
This is an AEMO autogenerated Market Notice.
[EventId:202501071015_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 07 January 2025 10:15
Issued by Australian Energy Market Operator Ltd at 1015 hrs on 7 January 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 7 January 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1015 hrs on 7 January 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
NEM Local Temperature Alerts for SA, VIC from 07 Jan 2025 to 11 Jan 2025
AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.
SA
Port Augusta Ap (39+ Deg C): 11th Jan
VIC
Mildura Ap (39+ Deg C): 11th Jan
The NEM Local Temperature Alert Levels are:
Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.
AEMO requests Market Participants to:
1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,
2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.
Further information is available at:
https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts
AEMO Operations Planning
[EventId:202501071000_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 07 January 2025 10:00
Issued by Australian Energy Market Operator Ltd at 1000 hrs on 7 January 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 7 January 2025.
Refer to market notice: 122924
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1000 hrs on 7 January 2025.
This is an AEMO autogenerated Market Notice.
[EventId:202501070835_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 07 January 2025 08:35
Issued by Australian Energy Market Operator Ltd at 0835 hrs on 7 January 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 7 January 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 0835 hrs on 7 January 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 06/01/2025
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 122896 is cancelled at 1430 hrs 06/01/2025.
Manager NEM Real Time Operations
NEM Local Temperature Alerts for SA from 06 Jan 2025 to 10 Jan 2025
AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.
SA
Port Augusta Ap (39+ Deg C): 9th Jan, 10th Jan
The NEM Local Temperature Alert Levels are:
Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.
AEMO requests Market Participants to:
1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,
2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.
Further information is available at:
https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts
AEMO Operations Planning
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 06/01/2025
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 122855 has been updated to the following:
[1.] From 1600 hrs 06/01/2025 to 1800 hrs 06/01/2025.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1087 MW.
Manager NEM Real Time Operations