Market Notices

126478PRICES SUBJECT TO REVIEW10/04/2025 05:10:15 PM

[EventId:202504101715_review] Prices for interval 10-Apr-2025 17:15 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1710 hrs on 10 April 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 10-Apr-2025 17:15.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
126476PRICES SUBJECT TO REVIEW10/04/2025 05:05:19 PM

[EventId:202504101710_review] Prices for interval 10-Apr-2025 17:10 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1705 hrs on 10 April 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 10-Apr-2025 17:10.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
126475PRICES SUBJECT TO REVIEW10/04/2025 05:00:15 PM

[EventId:202504101705_review] Prices for interval 10-Apr-2025 17:05 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1700 hrs on 10 April 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 10-Apr-2025 17:05.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
126474PRICES SUBJECT TO REVIEW10/04/2025 04:55:19 PM

[EventId:202504101700_review] Prices for interval 10-Apr-2025 17:00 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1655 hrs on 10 April 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 10-Apr-2025 17:00.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
126466GENERAL NOTICE10/04/2025 11:12:18 AM

Release of PEC-1 and combined V-SA limits - 11 April 2025

AEMO ELECTRICITY MARKET NOTICE

Refer to market notice 123956

AEMO, Transgrid and Electranet have reviewed the test results following the PEC Stage 1 testing on 31st January 2025. Hold points 4 and 5 can now be released.

The following limits will be released as of 1000hrs 11th April 2025:
- PEC-1 - 150 MW (both directions)
- Heywood + PEC1 - 750 MW from Vic to SA and 700 MW from SA to Vic
- The existing Heywood limits of 600 and 550 MW are not being changed.

With the release of these limits AEMO will be looking for testing opportunities for increases to Heywood as per the test plan: https://aemo.com.au/-/media/files/stakeholder_consultation/consultations/nem-consultations/2023/project-energyconnect-stage-1-and-hic-capacity-release/pec-stage-1-and-hic---final-test-program.pdf?la=en.

Ben Blake
AEMO Operations
     
126451PRICES SUBJECT TO REVIEW09/04/2025 05:25:23 PM

[EventId:202504091730_review] Prices for interval 09-Apr-2025 17:30 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1725 hrs on 9 April 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 09-Apr-2025 17:30.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
126450PRICES SUBJECT TO REVIEW09/04/2025 05:20:16 PM

[EventId:202504091725_review] Prices for interval 09-Apr-2025 17:25 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1720 hrs on 9 April 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 09-Apr-2025 17:25.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
126449PRICES SUBJECT TO REVIEW09/04/2025 05:15:19 PM

[EventId:202504091720_review] Prices for interval 09-Apr-2025 17:20 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1715 hrs on 9 April 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 09-Apr-2025 17:20.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
126447PRICES SUBJECT TO REVIEW09/04/2025 05:10:19 PM

[EventId:202504091715_review] Prices for interval 09-Apr-2025 17:15 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1710 hrs on 9 April 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 09-Apr-2025 17:15.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm