Market Notices

127349RESERVE NOTICE01/06/2025 07:12:29 PM

Cancellation of Actual (LOR1) condition in the NSW region - 01/06/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 01/06/2025

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.127348 is cancelled at 1910 hrs 01/06/2025.

Manager NEM Real Time Operations
     
127348RESERVE NOTICE01/06/2025 06:54:26 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 01/06/2025

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 01/06/2025

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1830 hrs.
The Actual LOR1 condition is forecast to exist until 1900 hrs

The capacity reserve requirement is 1666 MW
The minimum capacity reserve available is 1646 MW

Manager NEM Real Time Operations
     
127347RESERVE NOTICE01/06/2025 05:40:16 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW Region on 01/06/2025

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 01/06/2025

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1730 hrs.

The Actual LOR1 condition is forecast to exist until 1830 hrs.

The forecast capacity reserve requirement is 1694 MW.
The minimum capacity reserve available is 1568 MW.


Manager NEM Real Time Operations
     
127341NON-CONFORMANCE31/05/2025 12:50:15 PM

NON-CONFORMANCE Region QLD1 Saturday, 31 May 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Saturday, 31 May 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 31/05/2025 12:30 to 31/05/2025 12:50
Amount: 10 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
     
127340NON-CONFORMANCE30/05/2025 11:00:14 PM

NON-CONFORMANCE Region QLD1 Friday, 30 May 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Friday, 30 May 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 30/05/2025 22:25 to 30/05/2025 23:00
Amount: -32 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
     
127337NON-CONFORMANCE30/05/2025 01:00:13 PM

NON-CONFORMANCE Region QLD1 Friday, 30 May 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Friday, 30 May 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_1
Duration: 30/05/2025 11:50 to 30/05/2025 13:00
Amount: -63 MW
Constraint: NC-Q_MPP_1

Auto-generated on behalf of Manager NEM Real Time Operations
     
127326NON-CONFORMANCE28/05/2025 06:00:15 PM

NON-CONFORMANCE Region QLD1 Wednesday, 28 May 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Wednesday, 28 May 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_1
Duration: 28/05/2025 17:55 to 28/05/2025 18:00
Amount: -20 MW
Constraint: NC-Q_MPP_1

Auto-generated on behalf of Manager NEM Real Time Operations
     
127324INTER-REGIONAL TRANSFER28/05/2025 05:55:45 PM

Inter-regional transfer limit variation - Armidale Dumaresq 8C and Dumaresq Bulli 8M 330kV lines - NSW region - 28/05/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Armidale Dumaresq 8C and Dumaresq Bulli 8M 330kV lines - NSW region - 28/05/2025

At 1750 hrs 28/05/2025 there was a short notice outage of Armidale Dumaresq 8C and Dumaresq Bulli 8M 330kV lines.

The following constraint set(s) invoked at 1745 hrs 28/05/2025
N-ARDM_8C
N-X_8C+DM+TW_SVC

and the following constraint set(s) invoked at 1750 hrs 28/05/2025
I-BCDM_ONE
N-X_8L+DM+TW_SVC

These constraint set(s) contains equations with the following interconnectors on the LHS.
NSW1-QLD1,T-V-MNSP1,N-Q-MNSP1,V-S-MNSP1,V-SA

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
127322NON-CONFORMANCE28/05/2025 03:15:14 PM

NON-CONFORMANCE Region QLD1 Wednesday, 28 May 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Wednesday, 28 May 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 28/05/2025 12:30 to 28/05/2025 15:15
Amount: 26 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
     
X