Market Notices

126932MARKET INTERVENTION07/05/2025 02:38:21 PM

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO ELECTRICITY MARKET NOTICE

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0900 hrs 08/05/2025.

The foreseeable circumstance requiring the need for intervention is Voltage.

Manager NEM Real Time Operations
     
126925MARKET INTERVENTION07/05/2025 12:07:40 PM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 126906

Direction is cancelled from: 1200 hrs 07/05/2025

Manager NEM Real Time Operations
     
126923PRICES UNCHANGED06/05/2025 07:20:25 PM

[EventId:202505061900_confirmed] Prices for interval 06-May-2025 19:00 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1920 hrs on 6 May 2025

PRICES ARE NOW CONFIRMED for trading interval 06-May-2025 19:00.

In accordance with Market Notice 126913 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
126922PRICES UNCHANGED06/05/2025 07:20:24 PM

[EventId:202505061920_confirmed] Prices for interval 06-May-2025 19:20 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1920 hrs on 6 May 2025

PRICES ARE NOW CONFIRMED for trading interval 06-May-2025 19:20.

In accordance with Market Notice 126917 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
126921PRICES UNCHANGED06/05/2025 07:20:23 PM

[EventId:202505061915_confirmed] Prices for interval 06-May-2025 19:15 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1920 hrs on 6 May 2025

PRICES ARE NOW CONFIRMED for trading interval 06-May-2025 19:15.

In accordance with Market Notice 126916 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
126920PRICES UNCHANGED06/05/2025 07:20:22 PM

[EventId:202505061910_confirmed] Prices for interval 06-May-2025 19:10 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1920 hrs on 6 May 2025

PRICES ARE NOW CONFIRMED for trading interval 06-May-2025 19:10.

In accordance with Market Notice 126915 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
126919PRICES UNCHANGED06/05/2025 07:20:20 PM

[EventId:202505061905_confirmed] Prices for interval 06-May-2025 19:05 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1920 hrs on 6 May 2025

PRICES ARE NOW CONFIRMED for trading interval 06-May-2025 19:05.

In accordance with Market Notice 126914 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
126918PRICES UNCHANGED06/05/2025 07:20:22 PM

[EventId:202505061855_confirmed] Prices for interval 06-May-2025 18:55 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1920 hrs on 6 May 2025

PRICES ARE NOW CONFIRMED for trading interval 06-May-2025 18:55.

In accordance with Market Notice 126912 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
126907MARKET INTERVENTION06/05/2025 04:07:57 PM

Direction - SA region to AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region to AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

Refer to Market Notice 126848


In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN at 1600 hrs 06/05/2025
Type of resource: generating unit
Required actions: To synchronise and follow dispatch targets at 1200 hrs 07/05/2025
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: The synchronous generating units currently expected to be synchronised in SA will be inadequate to maintain sufficient Voltage Control in SA. Intervention is required to maintain the power system in a secure operating state
Expected duration: 0400 hrs 08/05/2025.

AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm