127132RECLASSIFY CONTINGENCY19/05/2025 02:34:02 AM

Cancellation of a Non-Credible Contingency Event: Bannaby - Mt Piper 5A6 500kV line and Bannaby - Mt Piper 5A7 500kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: NSW1

Lines: Bannaby - Mt Piper 5A6 500kV and Bannaby - Mt Piper 5A7 500kV

Cancellation time: 19/05/2025 02:33

Constraint set(s) revoked:
N-5A6+5A7_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1
VIC1-NSW1


Refer AEMO Electricity Market Notice 127131

Auto-generated on behalf of Manager NEM Real Time Operations
     
127131RECLASSIFY CONTINGENCY19/05/2025 01:33:11 AM

Reclassification of a Non-Credible Contingency Event: Bannaby - Mt Piper 5A6 500kV line and Bannaby - Mt Piper 5A7 500kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: NSW1

Lines: Bannaby - Mt Piper 5A6 500kV and Bannaby - Mt Piper 5A7 500kV

Duration: 19/05/2025 01:33 until further notice

Constraint set(s) invoked:
N-5A6+5A7_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1
VIC1-NSW1


Auto-generated on behalf of Manager NEM Real Time Operations
     
127129RECLASSIFY CONTINGENCY18/05/2025 05:49:04 PM

Cancellation of a Non-Credible Contingency Event: Armidale - Dumaresq 8C 330kV line and Armidale - Sapphire WF 8E 330kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: NSW1

Lines: Armidale - Dumaresq 8C 330kV and Armidale - Sapphire WF 8E 330kV

Cancellation time: 18/05/2025 17:48

Constraint set(s) revoked:
N-ARDM_ARSR_1PH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1


Refer AEMO Electricity Market Notice 127128

Auto-generated on behalf of Manager NEM Real Time Operations
     
127128RECLASSIFY CONTINGENCY18/05/2025 04:46:31 PM

Reclassification of a Non-Credible Contingency Event: Armidale - Dumaresq 8C 330kV line and Armidale - Sapphire WF 8E 330kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: NSW1

Lines: Armidale - Dumaresq 8C 330kV and Armidale - Sapphire WF 8E 330kV

Duration: 18/05/2025 16:46 until further notice

Constraint set(s) invoked:
N-ARDM_ARSR_1PH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1


Auto-generated on behalf of Manager NEM Real Time Operations
     
127119NON-CONFORMANCE18/05/2025 02:10:18 PM

NON-CONFORMANCE Region SA1 Sunday, 18 May 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE SA1 Region Sunday, 18 May 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: ADPBA1
Duration: 18/05/2025 13:30 to 18/05/2025 14:10
Amount: 6 MW
Constraint: NC-S_ADPBA1

Auto-generated on behalf of Manager NEM Real Time Operations
     
127115NON-CONFORMANCE17/05/2025 08:10:13 PM

NON-CONFORMANCE Region SA1 Saturday, 17 May 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE SA1 Region Saturday, 17 May 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: TB2B1
Duration: 17/05/2025 19:40 to 17/05/2025 20:10
Amount: 13 MW
Constraint: NC-S_TB2B1

Auto-generated on behalf of Manager NEM Real Time Operations
     
127104PRICES UNCHANGED16/05/2025 05:45:13 PM

[EventId:202505161745_confirmed] Prices for interval 16-May-2025 17:45 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1745 hrs on 16 May 2025

PRICES ARE NOW CONFIRMED for trading interval 16-May-2025 17:45.

In accordance with Market Notice 127098 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
127103PRICES UNCHANGED16/05/2025 05:45:18 PM

[EventId:202505161740_confirmed] Prices for interval 16-May-2025 17:40 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1745 hrs on 16 May 2025

PRICES ARE NOW CONFIRMED for trading interval 16-May-2025 17:40.

In accordance with Market Notice 127097 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
127102PRICES UNCHANGED16/05/2025 05:45:17 PM

[EventId:202505161735_confirmed] Prices for interval 16-May-2025 17:35 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1745 hrs on 16 May 2025

PRICES ARE NOW CONFIRMED for trading interval 16-May-2025 17:35.

In accordance with Market Notice 127096 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm