STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 07/02/2025
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 124154 has been updated at 1500 hrs 05/02/2025 to the following:
From 1630 hrs to 1900 hrs 07/02/2025.
The forecast capacity reserve requirement is 1162 MW.
The minimum capacity reserve available is 842 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
Update - Non-credible contingency event - TAS region - 03/02/2025
Update - Non-credible contingency event - TAS region - 03/02/2025
Refer AEMO Electricity Market Notice 124044
The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.
AEMO will cancel the reclassification of this event as a credible contingency event.
Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the NSW region - 05/02/2025
Cancellation of Actual (LOR1) condition in the NSW region - 05/02/2025
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.124176 is cancelled at 1444 hrs 05/02/2025.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 05/02/2025
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 05/02/2025
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1330 hrs.
The Actual LOR1 condition is forecast to exist until 1430 hrs
The capacity reserve requirement is 1320 MW
The minimum capacity reserve available is 1254 MW
Manager NEM Real Time Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 07/02/2025
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 124150 has been updated at 1200 hrs 05/02/2025 to the following:
From 1730 hrs to 1830 hrs 07/02/2025.
The forecast capacity reserve requirement is 1063 MW.
The minimum capacity reserve available is 967 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 07/02/2025
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 124143 has been updated at 1000 hrs 05/02/2025 to the following:
From 1630 hrs to 1900 hrs 07/02/2025.
The forecast capacity reserve requirement is 1161 MW.
The minimum capacity reserve available is 883 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 11/02/2025
The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 124147 is cancelled at 1000 hrs 05/02/2025.
No LOR2 condition is currently forecast in the SA region in the STPASA period.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 11/02/2025
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following period:
From 1800 hrs to 2030 hrs 11/02/2025.
The forecast capacity reserve requirement is 222 MW.
The minimum capacity reserve available is 180 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 07/02/2025
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 124066 has been updated at 0423 hrs 05/02/2025 to the following:
[1.] From 1600 hrs 07/02/2025 to 1930 hrs 07/02/2025.
The forecast capacity reserve requirement is 1144 MW.
The minimum capacity reserve available is 678 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations