127340NON-CONFORMANCE30/05/2025 11:00:14 PM

NON-CONFORMANCE Region QLD1 Friday, 30 May 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Friday, 30 May 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 30/05/2025 22:25 to 30/05/2025 23:00
Amount: -32 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
     
127337NON-CONFORMANCE30/05/2025 01:00:13 PM

NON-CONFORMANCE Region QLD1 Friday, 30 May 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Friday, 30 May 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_1
Duration: 30/05/2025 11:50 to 30/05/2025 13:00
Amount: -63 MW
Constraint: NC-Q_MPP_1

Auto-generated on behalf of Manager NEM Real Time Operations
     
127326NON-CONFORMANCE28/05/2025 06:00:15 PM

NON-CONFORMANCE Region QLD1 Wednesday, 28 May 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Wednesday, 28 May 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_1
Duration: 28/05/2025 17:55 to 28/05/2025 18:00
Amount: -20 MW
Constraint: NC-Q_MPP_1

Auto-generated on behalf of Manager NEM Real Time Operations
     
127322NON-CONFORMANCE28/05/2025 03:15:14 PM

NON-CONFORMANCE Region QLD1 Wednesday, 28 May 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Wednesday, 28 May 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 28/05/2025 12:30 to 28/05/2025 15:15
Amount: 26 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
     
127321NON-CONFORMANCE28/05/2025 02:35:19 AM

NON-CONFORMANCE Region QLD1 Wednesday, 28 May 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Wednesday, 28 May 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 28/05/2025 01:35 to 28/05/2025 02:35
Amount: 24 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
     
127306MARKET INTERVENTION27/05/2025 01:55:06 PM

Cancellation - AEMO Intervention Event - SA region 22/05/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - SA region 22/05/2025

Refer to Market Notice 127159

The AEMO Intervention Event and all associated directions are cancelled from 1400 hrs on 27/05/2025.


Manager NEM Real Time Operations
     
127305MARKET INTERVENTION27/05/2025 01:54:36 PM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 127276

Direction is cancelled from: 1400 hrs 27/05/2025

Manager NEM Real Time Operations
     
127276MARKET INTERVENTION26/05/2025 03:59:20 PM

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 127232

The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 1400 hrs 27/05/2025.

The direction update is issued at 1600 hrs 26/05/2025.

Manager NEM Real Time Operations
     
127232MARKET INTERVENTION25/05/2025 03:58:25 PM

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 127193

The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 27/05/2025.

The direction update is issued at 1600 hrs 25/05/2025.