STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 06/01/2025
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period[s]:
[1.] From 1600 hrs 06/01/2025 to 1700 hrs 06/01/2025.
The forecast capacity reserve requirement is 700 MW.
The minimum capacity reserve available is 509 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 06/01/2025
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 122587 has been updated at 1400 hrs 31/12/2024 to the following:
From 1500 hrs to 1900 hrs 06/01/2025.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 700 MW.
AEMO Operations
[EventId:202412311330_review] Prices for interval 31-Dec-2024 13:30 are subject to review
Issued by Australian Energy Market Operator Ltd at 1325 hrs on 31 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 31-Dec-2024 13:30.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202412311325_review] Prices for interval 31-Dec-2024 13:25 are subject to review
Issued by Australian Energy Market Operator Ltd at 1320 hrs on 31 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 31-Dec-2024 13:25.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202412311320_review] Prices for interval 31-Dec-2024 13:20 are subject to review
Issued by Australian Energy Market Operator Ltd at 1315 hrs on 31 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 31-Dec-2024 13:20.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202412311315_review] Prices for interval 31-Dec-2024 13:15 are subject to review
Issued by Australian Energy Market Operator Ltd at 1310 hrs on 31 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 31-Dec-2024 13:15.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202412311310_review] Prices for interval 31-Dec-2024 13:10 are subject to review
Issued by Australian Energy Market Operator Ltd at 1305 hrs on 31 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 31-Dec-2024 13:10.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202412311305_review] Prices for interval 31-Dec-2024 13:05 are subject to review
Issued by Australian Energy Market Operator Ltd at 1300 hrs on 31 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 31-Dec-2024 13:05.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 06/01/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:
1. From 1500 hrs to 1700 hrs 06/01/2025.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1142 MW.
2. From 1730 hrs to 1800 hrs 06/01/2025.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1328 MW.