PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 13/01/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 1730 hrs 13/01/2025 to 1830 hrs 13/01/2025.
The forecast capacity reserve requirement is 1815 MW.
The minimum capacity reserve available is 1796 MW.
Manager NEM Real Time Operations
Direction - SA region to Pelican Point Power Limited - PPCCGT PELICAN POINT
Direction - SA region to Pelican Point Power Limited - PPCCGT PELICAN POINT
Refer to Market Notice 123112
In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to Pelican Point Power Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT at 1600 hrs 12/01/2025
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 0830 hrs 13/01/2025
Services provided: Voltage Control
Circumstances necessitating the Direction:Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 1500 hrs 13/01/2025 / further notice.
Pelican Point Power Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.
Manager NEM Real Time Operations
Direction - SA region 12/01/2025
Direction - SA region 12/01/2025
In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1605 hrs on 12/01/2025.
Intervention pricing does not apply to this AEMO intervention event.
AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.
Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 15/01/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
From 1730 hrs 15/01/2025 to 1930 hrs 15/01/2025.
The forecast capacity reserve requirement is 1859 MW.
The minimum capacity reserve available is 1580 MW.
Manager NEM Real Time Operations
Cancellation - AEMO Intervention Event - SA region 11/01/2025
Cancellation - AEMO Intervention Event - SA region 11/01/2025
Refer to Market Notice 123044
The AEMO Intervention Event and all associated directions are cancelled from 1500 hrs on 12/01/2025.
Manager NEM Real Time Operations
Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT
Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT
Refer to Market Notice 123078
Direction is cancelled from: 1500 hrs 12/01/2025
Manager NEM Real Time Operations
Update - Foreseeable AEMO intervention in SA region
Update - Foreseeable AEMO intervention in SA region
Refer AEMO Electricity Market Notice 123104
AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0830 hrs 13/01/2025.
The foreseeable circumstance requiring the need for intervention is Voltage.
AEMO estimates that, in the absence of sufficient market response by 1600 hrs 12/01/2025, AEMO may need to intervene by issuing a direction.
Manager NEM Real Time Operations
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0800 hrs 13/01/2025.
The foreseeable circumstance requiring the need for intervention is Voltage.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Armidale-Sapphire 8E 330 kV line - NSW region - 12/01/2025
Inter-regional transfer limit variation - Armidale-Sapphire 8E 330 kV line - NSW region - 12/01/2025
A planned outage of Armidale-Sapphire 8E 330 kV line in the NSW region was scheduled from 0500 hrs 12/01/2025 to 1700 hrs 12/01/2025.
The outage has been completed and Armidale-Sapphire 8E 330kV line returned to service at 1015 hrs 12/01/2025
Constraint set(s) revoked:
N-ARSR_8E
N-DM_SVC
N-TW_SVC
N-X_8E+DM+TW+LS_SVC
Manager NEM Real Time Operations