126579POWER SYSTEM EVENTS16/04/2025 11:10:49 PM

Non-credible contingency event - QLD region - 16/04/2025

AEMO ELECTRICITY MARKET NOTICE.

Refer market notice: 126577

Non-credible contingency event - QLD region - 16/04/2025

At 2110 hrs the Greenbank - Molendinar 8825 275kV line tripped at the Molendinar end only.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.


Manager NEM Real Time Operations
     
126561SETTLEMENTS RESIDUE14/04/2025 06:15:29 PM

[EventId:202504141815_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 14 April 2025 18:15

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1815 hrs on 14 April 2025

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 14 April 2025.

Refer to market notice: 126550

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1815 hrs on 14 April 2025.

This is an AEMO autogenerated Market Notice.
     
126550SETTLEMENTS RESIDUE14/04/2025 05:30:24 PM

[EventId:202504141730_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 14 April 2025 17:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1730 hrs on 14 April 2025

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 14 April 2025.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1730 hrs on 14 April 2025.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
126517SETTLEMENTS RESIDUE11/04/2025 07:00:18 PM

[EventId:202504111900_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 11 April 2025 19:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1900 hrs on 11 April 2025

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 11 April 2025.

Refer to market notice: 126516

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1900 hrs on 11 April 2025.

This is an AEMO autogenerated Market Notice.
     
126516SETTLEMENTS RESIDUE11/04/2025 05:30:33 PM

[EventId:202504111730_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 11 April 2025 17:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1730 hrs on 11 April 2025

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 11 April 2025.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1730 hrs on 11 April 2025.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
126488SETTLEMENTS RESIDUE10/04/2025 07:00:27 PM

[EventId:202504101900_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 10 April 2025 19:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1900 hrs on 10 April 2025

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 10 April 2025.

Refer to market notice: 126477

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1900 hrs on 10 April 2025.

This is an AEMO autogenerated Market Notice.
     
126477SETTLEMENTS RESIDUE10/04/2025 05:05:22 PM

[EventId:202504101705_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 10 April 2025 17:05

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1705 hrs on 10 April 2025

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 10 April 2025.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1705 hrs on 10 April 2025.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
126463SETTLEMENTS RESIDUE09/04/2025 07:15:26 PM

[EventId:202504091915_NRM_VIC1_NSW1_stopped] NEGRES CONSTRAINT NRM_VIC1_NSW1 ceased operating from 09 April 2025 19:15

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1915 hrs on 9 April 2025

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to NSW - 9 April 2025.

Refer to market notice: 126459

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to NSW directional interconnector.

The negative residue constraint NRM_VIC1_NSW1 ceased operating at 1915 hrs on 9 April 2025.

This is an AEMO autogenerated Market Notice.
     
126461SETTLEMENTS RESIDUE09/04/2025 07:00:25 PM

[EventId:202504091900_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 09 April 2025 19:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1900 hrs on 9 April 2025

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 9 April 2025.

Refer to market notice: 126448

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1900 hrs on 9 April 2025.

This is an AEMO autogenerated Market Notice.
     