Market Notices

126986MARKET SYSTEMS11/05/2025 06:15:24 PM

INC0144295 | ALERT | Meter Data Management ¿ Degraded performance reported.

ELECTRICITY MARKET NOTICE
SERVICE INTERRUPTION - ALERT
AEMO is experiencing a service interruption relating Meter Data Management - Degraded performance to reports.
AEMO is working on the issue and will provide updates as more information becomes available.
For further enquiries please contact the AEMO Support Hub
Phone: 1300 236 600
Email: supporthub@aemo.com.au
AEMO IT Duty Manager
     
126985MARKET INTERVENTION11/05/2025 03:59:44 PM

Cancellation - Possible intervention to manage power system security in South Australia (SA) region 11/05/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation - Possible intervention to manage power system security in South Australia (SA) region 11/05/2025

Refer Market Notice 126981

AEMO no longer foresees a possible requirement for intervention to manage power system security in SA region. The advice of possible intervention is cancelled from 1600 hrs 11/05/2025.

Manager NEM Real Time Operations
     
126984MARKET INTERVENTION11/05/2025 03:27:46 PM

Cancellation - AEMO Intervention Event - SA region 10/05/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - SA region 10/05/2025

Refer to Market Notice 126977

The AEMO Intervention Event and all associated directions are cancelled from 1530 hrs on 11/05/2025.


Manager NEM Real Time Operations
     
126983MARKET INTERVENTION11/05/2025 03:27:24 PM

Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT

Refer to Market Notice 126978

Direction is cancelled from: 1530 hrs 11/05/2025

Manager NEM Real Time Operations
     
126982MARKET INTERVENTION11/05/2025 02:55:32 PM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

Refer to Market Notice 126979

Direction is cancelled from: 1500 hrs 11/05/2025

Manager NEM Real Time Operations
     
126981MARKET INTERVENTION11/05/2025 12:44:59 PM

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO ELECTRICITY MARKET NOTICE

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0830 hrs 12/05/2025.

The foreseeable circumstance requiring the need for intervention is Voltage.

Manager NEM Real Time Operations
     
126980NON-CONFORMANCE11/05/2025 12:15:11 PM

NON-CONFORMANCE Region VIC1 Sunday, 11 May 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Sunday, 11 May 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: COHUNSF1
Duration: 11/05/2025 12:00 to 11/05/2025 12:15
Amount: 17 MW
Constraint: NC-V_COHUNSF1

Auto-generated on behalf of Manager NEM Real Time Operations
     
126979MARKET INTERVENTION10/05/2025 04:00:41 PM

Direction - SA region to AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region to AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

Refer to Market Notice 126977.


In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN at 1600 hrs 10/05/2025
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 0100 hrs 11/05/2025
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: The synchronous generating units currently expected to be synchronised in SA will be inadequate to maintain sufficient Voltage Control in SA. Intervention is required to maintain the power system in a secure operating state
Expected duration: 1500 hrs 11/05/2025.

AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     
126978MARKET INTERVENTION10/05/2025 04:00:18 PM

Direction - SA region to Pelican Point Power Limited - PPCCGT PELICAN POINT

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region to Pelican Point Power Limited - PPCCGT PELICAN POINT

Refer to Market Notice 126977.


In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to Pelican Point Power Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT at 1600 hrs 10/05/2025
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 0130 hrs 11/05/2025
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: The synchronous generating units currently expected to be synchronised in SA will be inadequate to maintain sufficient Voltage Control in SA. Intervention is required to maintain the power system in a secure operating state
Expected duration: 1530 hrs 11/05/2025.

Pelican Point Power Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm