Market Notices

122442POWER SYSTEM EVENTS23/12/2024 04:44:55 PM

Non-credible contingency event - SA region - 23/12/2024

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - SA region - 23/12/2024

At 1632 hrs the Happy Valley - Morphett Vale East 275kV Line and the Morphett Vale - Cherry Gardens 275kV line tripped.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.

Manager NEM Real Time Operations
     
122435NON-CONFORMANCE23/12/2024 09:40:24 AM

NON-CONFORMANCE Region QLD1 Monday, 23 December 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Monday, 23 December 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 23/12/2024 09:25 to 23/12/2024 09:40
Amount: 36 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
     
122326MARKET SYSTEMS20/12/2024 04:16:29 PM

INC0139532 | Impact to Prudentials

AEMO ELECTRICITY MARKET NOTICE

SERVICE INTERRUPTION - ALERT

The service interruption relating to Prudentials & Settlements have now been resolved.
AEMO is working on the issue and will provide updates as more information becomes available.

For further enquiries please contact the AEMO Support Hub
Phone: 1300 236 600
Email: supporthub@aemo.com.au
AEMO IT Duty Manager
     
122290NON-CONFORMANCE20/12/2024 03:00:17 AM

NON-CONFORMANCE Region NSW1 Friday, 20 December 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Friday, 20 December 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: VP6
Duration: 20/12/2024 02:35 to 20/12/2024 03:00
Amount: -27 MW
Constraint: NC-N_VP6

Auto-generated on behalf of Manager NEM Real Time Operations
     
122281MARKET SYSTEMS19/12/2024 04:40:39 PM

INC0139532 - ALERT - Impact to Prudentials

AEMO ELECTRICITY MARKET NOTICE

SERVICE INTERRUPTION - ALERT

AEMO is experiencing a service interruption relating to: Prudentials & Settlements.

AEMO is working on the issue and will provide updates as more information becomes available.

For further enquiries please contact the AEMO Support Hub
Phone: 1300 236 600

Email: supporthub@aemo.com.au

AEMO IT Duty Manager
     
122117RESERVE NOTICE17/12/2024 05:44:06 PM

Cancellation of the Actual Lack Of Reserve Level 1 (LOR1) condition in the NSW Region on 17/12/2024

AEMO ELECTRICITY MARKET NOTICE

The Actual LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 122113 is cancelled at 1745 hrs 17/12/2024.

Manager NEM Real Time Operations
     
122113RESERVE NOTICE17/12/2024 03:44:28 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 17/12/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 17/12/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1530 hrs.
The Actual LOR1 condition is forecast to exist until 1800 hrs

The capacity reserve requirement is 1340 MW
The minimum capacity reserve available is 1082 MW

Manager NEM Real Time Operations
     
122095RESERVE NOTICE17/12/2024 11:40:17 AM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 17/12/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 122093 is cancelled at 1140 hrs 17/12/2024.

Manager NEM Real Time Operations
     
122093RESERVE NOTICE17/12/2024 10:19:24 AM

PDPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 17/12/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 122070 has been updated to the following:

[1.] From 1600 hrs 17/12/2024 to 1800 hrs 17/12/2024.
The forecast capacity reserve requirement is 745 MW.
The minimum capacity reserve available is 611 MW.


AEMO estimates the latest time at which it would need to intervene through an AEMO intervention event is 1400 hrs on 17/12/2024.


Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm