NON-CONFORMANCE Region NSW1 Tuesday, 14 January 2025
NON-CONFORMANCE NSW1 Region Tuesday, 14 January 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: VP5
Duration: 14/01/2025 05:55 to 14/01/2025 06:00
Amount: -19 MW
Constraint: NC-N_VP5
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the NSW region - 13/01/2025
Cancellation of Actual (LOR1) condition in the NSW region - 13/01/2025
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.123180 is cancelled at 2045 hrs 13/01/2025.
Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Monday, 13 January 2025
NON-CONFORMANCE NSW1 Region Monday, 13 January 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: WTAHB1
Duration: 13/01/2025 19:10 to 13/01/2025 19:20
Amount: -8 MW
Constraint: NC-N_WTAHB1
Auto-generated on behalf of Manager NEM Real Time Operations
Update - Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 13/01/2025
Update - Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 13/01/2025
Refer market notice: 123171
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1800 hrs.
The Actual LOR1 condition is forecast to exist until 2000 hrs.
The forecast capacity reserve requirement is 1365 MW.
The minimum capacity reserve available is 966 MW.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 13/01/2025
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 13/01/2025
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1630 hrs.
The Actual LOR1 condition is forecast to exist until 1700 hrs
The capacity reserve requirement is 1390 MW
The minimum capacity reserve available is 861 MW
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 13/01/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 123165 has been updated at 1600 hrs to the following:
[1.] From 1700 hrs 13/01/2025 to 1900 hrs 13/01/2025.
The forecast capacity reserve requirement is 915 MW.
The minimum capacity reserve available is 433 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 13/01/2025
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 1730 hrs 13/01/2025 to 1800 hrs 13/01/2025.
The forecast capacity reserve requirement is 917 MW.
The minimum capacity reserve available is 769 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Monday, 13 January 2025
NON-CONFORMANCE QLD1 Region Monday, 13 January 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_1
Duration: 13/01/2025 11:35 to 13/01/2025 13:50
Amount: 57 MW
Constraint: NC-Q_MPP_1
Auto-generated on behalf of Manager NEM Real Time Operations
[EventId:202501121020_confirmed] Prices for interval 12-Jan-2025 10:20 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1045 hrs on 12 January 2025
PRICES ARE NOW CONFIRMED for trading interval 12-Jan-2025 10:20.
In accordance with Market Notice 123080 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.