123602RESERVE NOTICE22/01/2025 08:14:17 PM

Cancellation of Actual (LOR1) condition in the QLD region - 22/01/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the QLD region - 22/01/2025

The Actual LOR1 Condition in the QLD Region advised in AEMO Electricity Market Notice No.123589 is cancelled at 2015 hrs 22/01/2025.

Manager NEM Real Time Operations
     
123593RESERVE NOTICE22/01/2025 06:14:27 PM

PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 22/01/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:


[1.] From 1830 hrs 22/01/2025 to 1900 hrs 22/01/2025.
The forecast capacity reserve requirement is 456 MW.
The minimum capacity reserve available is 343 MW.


AEMO is seeking a market response.

AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.


Manager NEM Real Time Operations
     
123589RESERVE NOTICE22/01/2025 05:47:39 PM

Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 22/01/2025

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 22/01/2025

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1930 hrs

The capacity reserve requirement is 854 MW
The minimum capacity reserve available is 543 MW

Manager NEM Real Time Operations
     
123549RESERVE NOTICE22/01/2025 08:56:34 AM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 28/01/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 123546 is cancelled at 0800 hrs 22/01/2025.

No LOR2 condition is currently forecast in the STPASA period.

AEMO Operations
     
123546RESERVE NOTICE22/01/2025 06:34:02 AM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 28/01/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

From 1630 hrs 28/01/2025 to 1700 hrs 28/01/2025.
The forecast capacity reserve requirement is 700 MW.
The minimum capacity reserve available is 570 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
123495RESERVE NOTICE20/01/2025 10:07:28 AM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 24/01/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 123464 is cancelled at 0900 hrs 20/01/2025.

No LOR2 condition is currently forecast in the STPASA period.

AEMO Operations
     
123464RESERVE NOTICE19/01/2025 05:24:36 AM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 24/01/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:

From 1530 hrs 24/01/2025 to 1600 hrs 24/01/2025.
The forecast capacity reserve requirement is 350 MW.
The minimum capacity reserve available is 247 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.


Manager NEM Real Time Operations
     
123451POWER SYSTEM EVENTS18/01/2025 04:19:58 PM

Update - Non-credible contingency event - NSW region - 15/01/2025

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - NSW region - 15/01/2025

Refer AEMO Electricity Market Notice 123354

At 1458 hrs the Tomago - Taree (963) 132kV line was returned to service. The Tomago - Brandy Hill (9C6) 132kV line was returned to service on 16/01/2025.

The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.

AEMO will not reclassify this event as a credible contingency event.

Manager NEM Real Time Operations
     
123445POWER SYSTEM EVENTS18/01/2025 02:06:59 PM

Update - Non-credible contingency event - NSW region - 17/01/2025

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - NSW region - 17/01/2025

Refer AEMO Electricity Market Notice 123406

At 1345 hrs the Buronga 330 kV B Bus was returned to service.

The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.

AEMO will not reclassify this event as a credible contingency event.

Manager NEM Real Time Operations
     