126786CONSTRAINTS29/04/2025 05:43:58 PM

Updated Victorian system normal voltage stability limit for the south-west Victoria

AEMO ELECTRICITY MARKET NOTICE

Refer to Market Notice 101368

AEMO has completed a review of the system normal voltage stability limit in the south-west Victoria as a result of Mortlake terminal station cut-in on the Haunted Gully to Tarrone 500 kV line.

The revised limit is increased by 100 MW on the cut-set from Haunted Gully to Moorabool and Mortlake to Moorabool 500 kV lines for flow towards Moorabool.

Full details on the limits advice are to be published shortly on the AEMO website: https://www.aemo.com.au/energy-systems/electricity/national-electricity-market-nem/system-operations/congestion-information-resource/limits-advice

The revised limit has been implemented at 1201 hrs on Tuesday 29th April 2025, by updating V^^V_NIL_SWVIC.

For further details on this constraint equation please contact terry.liu@aemo.com.au

Terry Liu
AEMO Operations
     
126783INTER-REGIONAL TRANSFER29/04/2025 04:51:17 PM

Inter-regional transfer limit variation - Eraring - Kemps Creek 5A1 500 kV line- NSW region - 29/04/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Eraring - Kemps Creek 5A1 500 kV line - NSW region - 29/04/2025

A planned outage of Eraring - Kemps Creek 5A1 500 kV line in the NSW region was scheduled from 0730 hrs 28/04/2025 to 1600 hrs 02/05/2025.

The outage has been completed and Eraring - Kemps Creek 5A1 500 kV line returned to service at 1650 hrs 29/04/2025

Constraint set revoked: N-ERKC_ONE

Manager NEM Real Time Operations
     
126773MARKET SYSTEMS29/04/2025 09:16:44 AM

Initial - CHG0102888 - Network Change Impacting Norwest Control Room Phone Network

Notification issued to: Market Notice

Notification Type: Initial

Change Type: Normal

Service/ Component: Local Area Network

Change Title: Network Change Impacting Norwest Control Room Phone Network

Change Start Date & Time: 30/04/2025 11:00:00

Change End Date & Time: 30/04/2025 16:00:00

Outage Start Date & Time: 30/04/2025 11:50:00

Outage End Date & Time: 30/04/2025 16:00:00

Environment: Production
Participant Impact and Requirements: 2 x 30 seconds outages to Norwest Control Room phone networks are expected on 30th April between 12 pm and 4 pm. You are hereby advised to maintain status quo and continue to reach out to Norwest control room as you would normally do and only call 02 8884 5291 or 02 8884 5292 if you have any trouble at all reaching them on their regular operating lines.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities.
     
126771GENERAL NOTICE29/04/2025 08:40:07 PM

Network Augmentation Commissioned - Vic Region - 29/04/2025

AEMO ELECTRICITY MARKET NOTICE


Network Augmentation Commissioned - Vic Region - 29/04/2025

At 2030hrs 29/04/2025, the existing Haunted Gully - Tarrone No1 500 kV transmission line has been cut in at Mortlake Power Station to create the following transmission line sections:

Mortlake PS - Tarrone No.1 500 kV transmission line
Mortlake PS - Haunted Gully No.1 500 kV transmission line

Manager NEM Real Time Operations
     
126770MARKET SYSTEMS28/04/2025 08:35:41 AM

CHG0102918 - Network Change Impacting Norwest and Brisbane Control Room Phone Network

Change Number: CHG0102918

Notification issued to: Market Notice

Notification Type: Initial

Change Type: Normal

Service/ Component: Local Area Network

Change Title: Network Change Impacting Norwest and Brisbane Control Room Phone Network

Change Start Date & Time: 01/05/2025 11:00:00

Change End Date & Time: 01/05/2025 16:00:00

Outage Start Date & Time: 01/05/2025 12:00:00

Outage End Date & Time: 01/05/2025 15:00:00

Environment: Production
Participant Impact and Requirements: Possibility of experiencing 2 x 30 seconds outages to Norwest and Brisbane Control Room phone networks on 1st May between 12 pm and 2 pm. You are hereby advised to maintain status quo and continue to reach out the Control rooms as you would normally do and only call Norwest on 02 8884 5291 or 02 8884 5292 and Brisbane on 0733473291 or 0733473292 if you have any trouble at all reaching them on their regular operating lines.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities.
     
126769MARKET SYSTEMS28/04/2025 08:32:51 AM

Initial - CHG0102888 - Network Change Impacting Norwest Control Room Phone Network

Notification issued to: Market Notice

Notification Type: Initial

Change Type: Normal

Service/ Component: Local Area Network

Change Title: Network Change Impacting Norwest Control Room Phone Network

Change Start Date & Time: 30/04/2025 11:00:00
Change End Date & Time: 30/04/2025 16:00:00
Outage Start Date & Time: 30/04/2025 11:50:00
Outage End Date & Time: 30/04/2025 16:00:00

Environment: Production
Participant Impact and Requirements: 2 x 30 seconds outages to Norwest Control Room phone networks are expected on 30th April between 12 pm and 4 pm. You are hereby advised to maintain status quo and continue to reach out to Norwest control room as you would normally do and only call 02 8884 5291 or 02 8884 5292 if you have any trouble at all reaching them on their regular operating lines.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities.
     
126740INTER-REGIONAL TRANSFER26/04/2025 11:57:04 AM

Inter-regional transfer limit variation - [outage element] - NSW region - 26/04/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - [outage element] - NSW region - 26/04/2025

At 1140 hrs 26/04/2025 there was a short notice outage of Griffith - Yanco 99J 132 kV Line.

The following constraint set(s) invoked at 1140 hrs 26/04/2025
N-GFYC-99J-C

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
126722GENERAL NOTICE24/04/2025 03:59:43 PM

Release of QNI limit from NSW to Qld - 29th April 2025

AEMO ELECTRICITY MARKET NOTICE

Refer to market notice 124749.

AEMO, Transgrid, Powerlink have reviewed the test results following the QNI minor testing on 16th February 2025. The next hold point can now be released.

The hold point of 950 MW from NSW to Qld will be implemented as of 1000 hrs 29th April 2025.

Please also refer to the published formal QNI minor testing information at the following link:
https://www.aemo.com.au/consultations/current-and-closed-consultations/qld-to-nsw-interconnector-qni-upgrade

Ben Blake
AEMO Operations
     
126712MARKET SYSTEMS24/04/2025 08:39:31 AM

Initial - CHG0102573 - There will be no access to the STTM Production services (SWEX/SWEXIE/MIS) for the duration of the outage

Change Number: CHG0102573

Notification issued to: Market Notice

Notification Type: Initial

Change Type: Normal

Service/ Component: STTM - Scheduling & Dispatch - SPI

Change Title: There will be no access to the STTM Production services (SWEX/SWEXIE/MIS) for the duration of the outage. Please access outside these hours.

Change Start Date & Time: 01/05/2025 18:30:00

Change End Date & Time: 01/05/2025 20:30:00

Outage Start Date & Time: 01/05/2025 18:30:00

Outage End Date & Time: 01/05/2025 20:30:00

Environment: Production

Participant Impact and Requirements: There will be no access to the STTM Production services (SWEX/SWEXIE/MIS) for the duration of the outage. Please access outside these hours.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities.
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm