PDPASA - Suspect Lack Of Reserve Level 2 (LOR2) in the QLD Region on 13/02/2025
AEMO considers that there is a suspect Forecast LOR2 condition for the QLD region for the following period[s]:
[1.] From 1830 hrs 13/02/2025 to 1930 hrs 13/02/2025.
The forecast capacity reserve requirement is 639 MW.
The minimum capacity reserve available is 480 MW.
AEMO is currently investigating this LOR2 forecast condition to confirm whether they are valid.
Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the SA region - 12/02/2025
Cancellation of Actual (LOR1) condition in the SA region - 12/02/2025
The Actual LOR1 Condition in the SA Region advised in AEMO Electricity Market Notice No.124572 is cancelled at 2040 hrs 12/02/2025.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 12/02/2025
Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 12/02/2025
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the SA region from 1830 hrs.
The Actual LOR1 condition is forecast to exist until 1930 hrs
The capacity reserve requirement is 524 MW
The minimum capacity reserve available is 470 MW
Manager NEM Real Time Operations
CHG0100111 | Completed | Pre-Production | Pre-Prod eMDM February Maintenance Release
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: MDM - Meter Data Management_PreProd
Change Title: Pre-Prod eMDM February Maintenance Release
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
[EventId:202502101600_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 10 February 2025 16:00
Issued by Australian Energy Market Operator Ltd at 1600 hrs on 10 February 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 10 February 2025.
Refer to market notice: 124442
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1600 hrs on 10 February 2025.
This is an AEMO autogenerated Market Notice.
[EventId:202502101505_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 10 February 2025 15:05
Issued by Australian Energy Market Operator Ltd at 1505 hrs on 10 February 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 10 February 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1505 hrs on 10 February 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202502101300_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 10 February 2025 13:00
Issued by Australian Energy Market Operator Ltd at 1300 hrs on 10 February 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 10 February 2025.
Refer to market notice: 124421
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1300 hrs on 10 February 2025.
This is an AEMO autogenerated Market Notice.
[EventId:202502101220_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 10 February 2025 12:20
Issued by Australian Energy Market Operator Ltd at 1220 hrs on 10 February 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 10 February 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1220 hrs on 10 February 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202502101200_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 10 February 2025 12:00
Issued by Australian Energy Market Operator Ltd at 1200 hrs on 10 February 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 10 February 2025.
Refer to market notice: 124415
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1200 hrs on 10 February 2025.
This is an AEMO autogenerated Market Notice.