Filter by category
Filter by Date
INC0139532 | Impact to Prudentials
SERVICE INTERRUPTION - ALERT
The service interruption relating to Prudentials & Settlements have now been resolved.
AEMO is working on the issue and will provide updates as more information becomes available.
For further enquiries please contact the AEMO Support Hub
Phone: 1300 236 600
Email: supporthub@aemo.com.au
AEMO IT Duty Manager
Direction - SA region to AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Direction - SA region to AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer to Market Notice 122279
In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN at 1445 hrs 20/12/2024
Type of resource: generating unit
Required actions: Synchronise and follow dispatch targets at 0400 hrs 21/12/2024
Services provided: Voltage Control
Circumstances necessitating the Direction:Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 0400 hrs 22/12/2024 / further notice.
AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer to Market Notice 122277
The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 22/12/2024.
The direction update is issued at 1445 hrs 20/12/2024.
Manager NEM Real Time Operations
Cancellation of Forecast Minimum System Load MSL2 event in the VIC Region on 22/12/2024
Cancellation - Forecast MSL2 - VIC Region at 1200 hrs 20/12/2024.
Refer to Market Notice 122305 for MSL2.
AEMO Operations
NEM Local Temperature Alerts for QLD from 20 Dec 2024 to 24 Dec 2024
AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.
QLD
Rockhampton Ap (39+ Deg C): 24th Dec
The NEM Local Temperature Alert Levels are:
Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.
AEMO requests Market Participants to:
1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,
2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.
Further information is available at:
https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts
AEMO Operations Planning
Forecast Minimum System Load (MSL2) condition in the VIC region on 22/12/2024
AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC region on 22/12/2024.
Minimum System Load (MSL) conditions are forecast when regional demand is less than the relevant MSL threshold. The advisory MSL thresholds are:
o MSL1 - 1825 MW
o MSL2 - 1325 MW
o MSL3 - 825 MW
The regional demand is forecast to be below the MSL2 threshold for the following period:
From 1230 hrs 22/12/2024 to 1300 hrs 22/12/2024. Minimum regional demand is forecast to be 1284 MW at 1300 hrs.
Forecast regional demand (DEMAND50) is published in Short Term and Pre-Dispatch PASA region solution reports available on Market Data NEMWEB: https://aemo.com.au/en/energy-systems/electricity/national-electricity-market-nem/data-nem/market-data-nemweb .
AEMO Operations
Update Direction - Synergen Power Pty Limited - MINTARO MINTARO GAS
Update Direction - Synergen Power Pty Limited - MINTARO MINTARO GAS
Refer to Market Notice 122283
The MINTARO MINTARO GAS direction is now expected to start at 0830 hrs 20/12/2024.
The direction update is issued at 0725 hrs 20/12/2024.
Manager NEM Real Time Operations
Cancellation of Forecast Minimum System Load (MSL) MSL2 event in the VIC Region on 22/12/2024.
Cancellation of Forecast Minimum System Load (MSL) MSL2 event in the VIC Region on 22/12/2024.
Cancellation - Forecast MSL2- VIC Region at 2030 hrs 22/12/2024.
Refer to Market Notice 122275for MSL2.
Manager NEM Real Time Operations
Direction - SA region to Synergen Power Pty Limited - MINTARO MINTARO GAS
Direction - SA region to Synergen Power Pty Limited - MINTARO MINTARO GAS
Refer to Market Notice 122276
In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to Synergen Power Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
Direction issued to: Synergen Power Pty Limited - MINTARO MINTARO GAS at 1700 hrs 19/12/2024
Type of resource: generating unit
Required actions: Synchronise and follow dispatch targets at 0800 hrs 20/12/2024
Services provided: Voltage Control
Circumstances necessitating the Direction:Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 0400 hrs 21/12/2024.
Synergen Power Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.
Manager NEM Real Time Operations