PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 30/05/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 1730 hrs 30/05/2025 to 1800 hrs 30/05/2025.
The forecast capacity reserve requirement is 1738 MW.
The minimum capacity reserve available is 1669 MW.
Manager NEM Real Time Operations
Cancellation of the Reclassification of a Non-Credible Contingency Event: Loss of the Sheffield - Burnie No. 1 220kV Line, Sheffield - Burnie No. 2 110kV Line and the Ulverstone - Emu Bay 110kV Line in TAS1 due to lightning
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event .
Based on advice received from the asset owner, AEMO no longer considers the trip of the Sheffield - Burnie No. 1 220kV Line, Sheffield - Burnie No. 2 110kV Line and the Ulverstone - Emu Bay 110kV Line in TAS1 due to lightning as a credible contingency when there is lightning activity in the vicinity.
Accordingly the reclassification as a credible contingency is cancelled .
Region: TAS1
Element: Sheffield - Burnie No. 1 220kV Line, Sheffield - Burnie No. 2 110kV Line and the Ulverstone - Emu Bay 110kV Line
Cancellation time: 29/05/2025 1600 hrs
Constraint set(s) revoked: NONE
Refer AEMO Electricity Market Notices 125566
Manager NEM Real Time Operations
Update - Non-credible contingency event - NSW region - 07/03/2025
Update - Non-credible contingency event - NSW region - 07/03/2025
Refer AEMO Electricity Market Notice 125536
The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.
AEMO will no longer reclassify this event as a credible contingency event.
Region: NSW
Elements:
- Lismore132 - Mullumbimby 9U6 132kV Line
- Lismore132 - Mullumbimby 9U7 132kV Line
- Ewingsdale - Mullumbimby 9G5 132kV Line
Duration: 1730 hrs 11/03/2025 until 1230 hrs 27/05/2025
Constraint set(s) invoked: NONE
Manager NEM Real Time Operations
Cancellation of the reclassification of a Non-Credible Contingency Event: Brinkworth-Davenport, Brinkworth-Templers West and Para-Templers West 275kV lines in SA due to severe weather warning .
Cancellation of the reclassification of a non-credible contingency event as a credible contingency event due to severe weather warning.
AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any severe weather warning in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: SA
Lines: Brinkworth-Davenport, Brinkworth-Templers West and Para-Templers West 275kV lines
Cancellation time: 1150 hrs 27/05/2025
Constraint set(s) revoked: Nil
Refer AEMO Electricity Market Notice 127230
Manager NEM Real Time Operations
Cancellation of a Non-Credible Contingency Event: Bayswater - Mt Piper No.5A3 500kV line and Wollar - Mt Piper No.5A5 500kV line in NSW1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: NSW1
Lines: Bayswater - Mt Piper No.5A3 500kV and Wollar - Mt Piper No.5A5 500kV
Cancellation time: 27/05/2025 00:33
Constraint set(s) revoked:
NONE
Refer AEMO Electricity Market Notice 127295
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation of a Non-Credible Contingency Event: Burnie - Port Latta - Smithton 1 110kV line and Burnie - Port Latta - Smithton 2 110kV line in TAS1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: TAS1
Lines: Burnie - Port Latta - Smithton 1 110kV and Burnie - Port Latta - Smithton 2 110kV
Cancellation time: 27/05/2025 00:12
Constraint set(s) revoked:
NONE
Refer AEMO Electricity Market Notice 127286
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation of a Non-Credible Contingency Event: Norwood - Scottsdale 1 110kV line and Norwood-Derby-Scottsdale 110kV line in TAS1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: TAS1
Lines: Norwood - Scottsdale 1 110kV and Norwood-Derby-Scottsdale 110kV
Cancellation time: 27/05/2025 00:12
Constraint set(s) revoked:
NONE
Refer AEMO Electricity Market Notice 127291
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation of a Non-Credible Contingency Event: George Town - Sheffield 1&2 220kV + Nyrstar&Temco line and line in TAS1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: TAS1
Lines: George Town - Sheffield 1&2 220kV + Nyrstar&Temco and
Cancellation time: 27/05/2025 00:08
Constraint set(s) revoked:
T-GTSH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
T-V-MNSP1
Refer AEMO Electricity Market Notice 127288
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation of a Non-Credible Contingency Event: Ulverstone - Emu Bay 110kV line and Sheffield - Paloona - Ulverstone 1 & 2 110kV line in TAS1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: TAS1
Lines: Ulverstone - Emu Bay 110kV and Sheffield - Paloona - Ulverstone 1 & 2 110kV
Cancellation time: 26/05/2025 23:53
Constraint set(s) revoked:
NONE
Refer AEMO Electricity Market Notice 127289
Auto-generated on behalf of Manager NEM Real Time Operations