Inter-regional transfer limit variation - Lismore SVC - NSW region - 07/03/2025
Inter-regional transfer limit variation - Lismore SVC - NSW region - 07/03/2025
At 0720 hrs 07/03/2025 there was an unplanned outage of Lismore SVC.
The following constraint set(s) invoked at 0725 hrs 07/03/2025
N-LS_VC1
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-Regional Transfer limit variation - Directlink - NSW Region
Refer to Market Notice 125355.
Inter-Regional Transfer limit variation - Directlink - NSW Region
There has been an unplanned outage of the No 1 and 2 cables of Directlink .
The following constraint set was invoked at 0620 hrs 07/03/2025
N-X_MBTE_3
The constraint set contains the following interconnector on the left hand side.
N-Q-MNSP1
Refer AEMO Network Outage Scheduler (NOS) for further details.
Manager NEM Real Time Operations
[EventId:202503061820_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 06 March 2025 18:20
Issued by Australian Energy Market Operator Ltd at 1820 hrs on 6 March 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 6 March 2025.
Refer to market notice: 125341
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1820 hrs on 6 March 2025.
This is an AEMO autogenerated Market Notice.
[EventId:202503061600_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 06 March 2025 16:00
Issued by Australian Energy Market Operator Ltd at 1600 hrs on 6 March 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 6 March 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1600 hrs on 6 March 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer to Market Notice 125275
TORRB2 TORRENS ISLAN at 0730 hrs 05/03/2025 to Remain synchronised and follow dispatch targets.
The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 08/03/2025.
The direction update is issued at 1600 hrs 06/03/2025.
Manager NEM Real Time Operations
Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT
Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT
Refer to Market Notice 125274
PPCCGT PELICAN POINT at 0700 hrs 05/03/2025 to Remain synchronised and follow dispatch targets.
The PPCCGT PELICAN POINT direction is now expected to stay in place until 1700 hrs 07/03/2025.
The direction update is issued at 1600 hrs 06/03/2025.
Manager NEM Real Time Operations
Inter-Regional Transfer limit variation - Directlink - NSW Region
Inter-Regional Transfer limit variation - Directlink - NSW Region
There has been an unplanned outage of the No. 1 and 2 Legs of Directlink.
The following constraint set was invoked at 1125 hrs 06/03/2025.
N-X_MBTE_3
The constraint set contains the following interconnector on the left hand side.
N-Q-MNSP1
Refer AEMO Network Outage Scheduler (NOS) for further details.
Manager NEM Real Time Operations
[EventId:202503051905_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 05 March 2025 19:05
Issued by Australian Energy Market Operator Ltd at 1905 hrs on 5 March 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 5 March 2025.
Refer to market notice: 125282
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1905 hrs on 5 March 2025.
This is an AEMO autogenerated Market Notice.
[EventId:202503051805_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 05 March 2025 18:05
Issued by Australian Energy Market Operator Ltd at 1805 hrs on 5 March 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 5 March 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1805 hrs on 5 March 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.