Inter-regional transfer limit variation - Collector -Yass 3L 330kV Line - NSW region - 14/04/2025
Inter-regional transfer limit variation - Collector -Yass 3L 330kV Line - NSW region - 14/04/2025
A planned outage of the Collector -Yass 3L 330kV Line in the NSW region was scheduled from 0700 hrs 12/04/2025 to 1700 hrs 16/04/2025.
The outage has been completed and the Collector -Yass 3L 330kV Line returned to service at 1735 hrs 14/04/2025
Constraint set(s) revoked: N-CTYS_3L_WG_CLOSE
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 14/04/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 1730 hrs 14/04/2025 to 1800 hrs 14/04/2025.
The forecast capacity reserve requirement is 1537 MW.
The minimum capacity reserve available is 1365 MW.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 14/04/2025
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 126538 is cancelled at 1600 hrs 14/04/2025.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 14/04/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 1700 hrs 14/04/2025 to 1830 hrs 14/04/2025.
The forecast capacity reserve requirement is 1595 MW.
The minimum capacity reserve available is 1141 MW.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 14/04/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 1730 hrs 14/04/2025 to 1800 hrs 14/04/2025.
The forecast capacity reserve requirement is 1632 MW.
The minimum capacity reserve available is 1392 MW.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Greenbank SVC- QLD region - 11/04/2025
Inter-regional transfer limit variation - Greenbank SVC - QLD region - 11/04/2025
At 1600 hrs 11/04/2025 there was an unplanned outage of Greenbank SVC.
The following constraint set(s) invoked at 1605 hrs 11/04/2025
Q-GB_VC
This constraint set(s) contains equations with the following interconnectors on the LHS.
NSW1-QLD1,N-Q-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 14/04/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
From 1730 hrs to 1800 hrs 14/04/2025.
The forecast capacity reserve requirement is 1680 MW.
The minimum capacity reserve available is 1608 MW.
AEMO Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 10/04/2025
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 126467 is cancelled at 1540 hrs 10/04/2025.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 10/04/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 1800 hrs 10/04/2025 to 1830 hrs 10/04/2025.
The forecast capacity reserve requirement is 1595 MW.
The minimum capacity reserve available is 1577 MW.
Manager NEM Real Time Operations