Market Notices

123655PRICES SUBJECT TO REVIEW24/01/2025 11:10:21 AM

[EventId:202501241115_review] Prices for interval 24-Jan-2025 11:15 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1110 hrs on 24 January 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 24-Jan-2025 11:15.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
123653PRICES SUBJECT TO REVIEW24/01/2025 11:05:19 AM

[EventId:202501241110_review] Prices for interval 24-Jan-2025 11:10 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1105 hrs on 24 January 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 24-Jan-2025 11:10.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
123651PRICES SUBJECT TO REVIEW24/01/2025 11:00:23 AM

[EventId:202501241105_review] Prices for interval 24-Jan-2025 11:05 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1100 hrs on 24 January 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 24-Jan-2025 11:05.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
123649RESERVE NOTICE24/01/2025 10:22:15 AM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 24/01/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:


[1.] From 1800 hrs 24/01/2025 to 1930 hrs 24/01/2025.
The forecast capacity reserve requirement is 854 MW.
The minimum capacity reserve available is 759 MW.


Manager NEM Real Time Operations
     
123645RESERVE NOTICE24/01/2025 04:46:13 AM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the Qld Region on 24/01/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the Qld region advised in AEMO Electricity Market Notice No. 123637 is cancelled at 0445 hrs 24/01/2025

Manager NEM Real Time Operations
     
123637RESERVE NOTICE23/01/2025 05:23:26 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 24/01/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:


[1.] From 1900 hrs 24/01/2025 to 1930 hrs 24/01/2025.
The forecast capacity reserve requirement is 854 MW.
The minimum capacity reserve available is 830 MW.


Manager NEM Real Time Operations
     
123626RESERVE NOTICE23/01/2025 03:05:29 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 28/01/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 123523 is cancelled at 1400 hrs 23/01/2025.

No LOR condition is currently forecast in the STPASA period.

AEMO Operations
     
123602RESERVE NOTICE22/01/2025 08:14:17 PM

Cancellation of Actual (LOR1) condition in the QLD region - 22/01/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the QLD region - 22/01/2025

The Actual LOR1 Condition in the QLD Region advised in AEMO Electricity Market Notice No.123589 is cancelled at 2015 hrs 22/01/2025.

Manager NEM Real Time Operations
     
123589RESERVE NOTICE22/01/2025 05:47:39 PM

Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 22/01/2025

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 22/01/2025

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1930 hrs

The capacity reserve requirement is 854 MW
The minimum capacity reserve available is 543 MW

Manager NEM Real Time Operations
     