Cancellation of Actual (LOR1) condition in the NSW region - 10/04/2025
Cancellation of Actual (LOR1) condition in the NSW region - 10/04/2025
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.126487 is cancelled at 1910 hrs 10/04/2025.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 10/04/2025
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 10/04/2025
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1830 hrs
The capacity reserve requirement is 1585 MW
The minimum capacity reserve available is 1337 MW
Manager NEM Real Time Operations
[EventId:202504101700_confirmed] Prices for interval 10-Apr-2025 17:00 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1725 hrs on 10 April 2025
PRICES ARE NOW CONFIRMED for trading interval 10-Apr-2025 17:00.
In accordance with Market Notice 126474 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202504101725_confirmed] Prices for interval 10-Apr-2025 17:25 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1725 hrs on 10 April 2025
PRICES ARE NOW CONFIRMED for trading interval 10-Apr-2025 17:25.
In accordance with Market Notice 126480 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202504101720_confirmed] Prices for interval 10-Apr-2025 17:20 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1725 hrs on 10 April 2025
PRICES ARE NOW CONFIRMED for trading interval 10-Apr-2025 17:20.
In accordance with Market Notice 126479 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202504101715_confirmed] Prices for interval 10-Apr-2025 17:15 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1725 hrs on 10 April 2025
PRICES ARE NOW CONFIRMED for trading interval 10-Apr-2025 17:15.
In accordance with Market Notice 126478 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202504101710_confirmed] Prices for interval 10-Apr-2025 17:10 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1725 hrs on 10 April 2025
PRICES ARE NOW CONFIRMED for trading interval 10-Apr-2025 17:10.
In accordance with Market Notice 126476 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202504101705_confirmed] Prices for interval 10-Apr-2025 17:05 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1725 hrs on 10 April 2025
PRICES ARE NOW CONFIRMED for trading interval 10-Apr-2025 17:05.
In accordance with Market Notice 126475 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
Update - Inter-regional transfer limit variation - APD - Heywood - Mortlake 500 kV line - VIC region - 10/04/2025
Update - Inter-regional transfer limit variation - APD - Heywood - Mortlake 500 kV line - VIC region - 10/04/2025
Refer to Market Notice 126464.
The cause of the unplanned outage of APD - Heywood - Mortlake 500 kV line in the VIC region has been identified and resolved. The outage has been completed and the APD - Heywood - Mortlake 500 kV line returned to service at 0948 hrs 10/04/2025
Constraint set(s) revoked: V-HYMO
Manager NEM Real Time Operations