Reclassification of a Non-Credible Contingency Event: Chalumbin - Turkinje No.7165 132 kV line and Chalumbin - Turkinje No.7166 132 kV line in QLD1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: QLD1
Lines: Chalumbin - Turkinje No.7165 132 kV and Chalumbin - Turkinje No.7166 132 kV
Duration: 06/03/2025 13:41 until further notice
Constraint set(s) invoked:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Guybal Munjan - Chalumbin 857 275kV line line and Guybal Munjan - Chalumbin 858 275kV line line in QLD1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: QLD1
Lines: Guybal Munjan - Chalumbin 857 275kV line and Guybal Munjan - Chalumbin 858 275kV line
Duration: 06/03/2025 13:38 until further notice
Constraint set(s) invoked:
Q-RSCH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations
[EventId:202503061315_confirmed] Prices for interval 06-Mar-2025 13:15 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1335 hrs on 6 March 2025
PRICES ARE NOW CONFIRMED for trading interval 06-Mar-2025 13:15.
In accordance with Market Notice 125314 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202503061335_confirmed] Prices for interval 06-Mar-2025 13:35 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1335 hrs on 6 March 2025
PRICES ARE NOW CONFIRMED for trading interval 06-Mar-2025 13:35.
In accordance with Market Notice 125319 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202503061330_confirmed] Prices for interval 06-Mar-2025 13:30 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1335 hrs on 6 March 2025
PRICES ARE NOW CONFIRMED for trading interval 06-Mar-2025 13:30.
In accordance with Market Notice 125318 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202503061325_confirmed] Prices for interval 06-Mar-2025 13:25 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1335 hrs on 6 March 2025
PRICES ARE NOW CONFIRMED for trading interval 06-Mar-2025 13:25.
In accordance with Market Notice 125317 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202503061320_confirmed] Prices for interval 06-Mar-2025 13:20 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1335 hrs on 6 March 2025
PRICES ARE NOW CONFIRMED for trading interval 06-Mar-2025 13:20.
In accordance with Market Notice 125316 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202503061310_confirmed] Prices for interval 06-Mar-2025 13:10 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1335 hrs on 6 March 2025
PRICES ARE NOW CONFIRMED for trading interval 06-Mar-2025 13:10.
In accordance with Market Notice 125313 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
Reclassification of a Non-Credible Contingency Event: Collinsville - Stoney Creek 7306 132KV LINE line and Collinsville - Newlands 7121 132KV LINE line in QLD1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: QLD1
Lines: Collinsville - Stoney Creek 7306 132KV LINE and Collinsville - Newlands 7121 132KV LINE
Duration: 06/03/2025 13:13 until further notice
Constraint set(s) invoked:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations