126093NON-CONFORMANCE30/03/2025 11:30:19 PM

NON-CONFORMANCE Region QLD1 Sunday, 30 March 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Sunday, 30 March 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_1
Duration: 30/03/2025 21:45 to 30/03/2025 23:30
Amount: 26 MW
Constraint: NC-Q_MPP_1

Auto-generated on behalf of Manager NEM Real Time Operations
     
126091NON-CONFORMANCE30/03/2025 08:15:19 PM

NON-CONFORMANCE Region QLD1 Sunday, 30 March 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Sunday, 30 March 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_1
Duration: 30/03/2025 17:25 to 30/03/2025 20:15
Amount: -40 MW
Constraint: NC-Q_MPP_1

Auto-generated on behalf of Manager NEM Real Time Operations
     
126086NON-CONFORMANCE30/03/2025 06:15:11 PM

NON-CONFORMANCE Region QLD1 Sunday, 30 March 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Sunday, 30 March 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 30/03/2025 15:45 to 30/03/2025 18:15
Amount: -113 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
     
126057NON-CONFORMANCE30/03/2025 04:50:22 AM

NON-CONFORMANCE Region QLD1 Sunday, 30 March 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Sunday, 30 March 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_1
Duration: 30/03/2025 04:40 to 30/03/2025 04:50
Amount: -24 MW
Constraint: NC-Q_MPP_1

Auto-generated on behalf of Manager NEM Real Time Operations
     
126045NON-CONFORMANCE29/03/2025 05:00:17 PM

NON-CONFORMANCE Region QLD1 Saturday, 29 March 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Saturday, 29 March 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: CALL_B_2
Duration: 29/03/2025 16:55 to 29/03/2025 17:00
Amount: -11 MW
Constraint: NC-Q_CALL_B_2

Auto-generated on behalf of Manager NEM Real Time Operations
     
126016MARKET SYSTEMS28/03/2025 02:07:44 PM

CHG0102344 - Maintenance activities to be performed on the Declared Wholesale Gas Market Systems Pre-Production.

Change Number: CHG0102344

Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Declared Wholesale Gas Market (DWGM)
Change Title: Maintenance activities to be performed on the Declared Wholesale Gas Market Systems Pre-Production.
Change Start Date & Time: 02/04/2025 08:00:00
Change End Date & Time: 02/04/2025 17:30:00
Outage Start Date & Time: 02/04/2025 09:00:00
Outage End Date & Time: 02/04/2025 12:00:00
Environment: Pre-Production
Participant Impact and Requirements: This is a regular procedure to allow routine maintenance. short service outages over the day for DWGM services, includiing MIBB and Web Exchanger.

Pre-Production Declared Wholesale Gas Market Systems (DWGM)

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities .
     
126015MARKET SYSTEMS28/03/2025 02:00:12 PM

CHG0101896 - EMMS Pre-Production Systems will be transferred to the alternative datacentre for maintenance activities .

Change Number: CHG0101896

Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Electricity Market Management System_PreProd
Change Title: EMMS Pre-Production Systems will be transferred to the alternative datacentre for maintenance activities .
Change Start Date & Time: 01/04/2025 08:00:00
Change End Date & Time: 11/04/2025 17:00:00
Outage Start Date & Time: 03/04/2025 08:00:00
Outage End Date & Time: 03/04/2025 22:00:00
Environment: Pre-Production
Participant Impact and Requirements: EMMS Pre-Production Systems will be transferred to the alternative datacentre for maintenance activities. Maintenance activities will be conducted on the following dates:
1/04/2025
3/04/2025
8/04/2025

During the window,FPP calculations may be delayed at various points.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities .
     
126014MARKET SYSTEMS28/03/2025 01:57:12 PM

CHG0101950 - Telco Outage Notification - Telstra Brisbane Indial (07 3347 XXXX-XXXX)

Change Number: CHG0101950

Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Cisco IP Phone
Change Title: Telco Outage Notification - Telstra Brisbane Indial (07 3347 XXXX-XXXX)
Change Start Date & Time: 01/04/2025 01:00:00
Change End Date & Time: 01/04/2025 06:00:00
Outage Start Date & Time: 01/04/2025 01:00:00
Outage End Date & Time: 01/04/2025 06:00:00
Environment: Production
Participant Impact and Requirements: External/Market

Outage Duration:
1 x 15 minutes during the window

Impacts:
Reduced redundancy for Inbound and Outbound Calls (automatically rerouted via Sydney).

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities .
     
125963POWER SYSTEM EVENTS26/03/2025 04:20:27 PM

Non-credible contingency event - TAS region - 26/03/2025

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - TAS region - 26/03/2025

At 1551 hrs the Palmerston A 220kV Bus tripped.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

Approximately 40MW of generation was disconnected.

The cause of this non credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.

AEMO will not reclassify this event as a credible contingency event.


Manager NEM Real Time Operations
     