Filter by category
Filter by Date
Update - Non-credible contingency event - SA region - 23/12/2024
Update - Non-credible contingency event - SA region - 23/12/2024
Refer AEMO Electricity Market Notice 122442
At 2036 hrs the Happy Valley - Morphett Vale East and the Morphett Vale - Cherry Gardens 275kV lines were returned to service.
The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.
AEMO will not reclassify this event as a credible contingency event.
Manager NEM Real Time Operations
Non-credible contingency event - SA region - 23/12/2024
Non-credible contingency event - SA region - 23/12/2024
At 1632 hrs the Happy Valley - Morphett Vale East 275kV Line and the Morphett Vale - Cherry Gardens 275kV line tripped.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Monday, 23 December 2024
NON-CONFORMANCE QLD1 Region Monday, 23 December 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_2
Duration: 23/12/2024 09:25 to 23/12/2024 09:40
Amount: 36 MW
Constraint: NC-Q_MPP_2
Auto-generated on behalf of Manager NEM Real Time Operations
INC0139532 | Impact to Prudentials
SERVICE INTERRUPTION - ALERT
The service interruption relating to Prudentials & Settlements have now been resolved.
AEMO is working on the issue and will provide updates as more information becomes available.
For further enquiries please contact the AEMO Support Hub
Phone: 1300 236 600
Email: supporthub@aemo.com.au
AEMO IT Duty Manager
NON-CONFORMANCE Region NSW1 Friday, 20 December 2024
NON-CONFORMANCE NSW1 Region Friday, 20 December 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: VP6
Duration: 20/12/2024 02:35 to 20/12/2024 03:00
Amount: -27 MW
Constraint: NC-N_VP6
Auto-generated on behalf of Manager NEM Real Time Operations
INC0139532 - ALERT - Impact to Prudentials
SERVICE INTERRUPTION - ALERT
AEMO is experiencing a service interruption relating to: Prudentials & Settlements.
AEMO is working on the issue and will provide updates as more information becomes available.
For further enquiries please contact the AEMO Support Hub
Phone: 1300 236 600
Email: supporthub@aemo.com.au
AEMO IT Duty Manager
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 17/12/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 122093 is cancelled at 1140 hrs 17/12/2024.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 17/12/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 122070 has been updated to the following:
[1.] From 1600 hrs 17/12/2024 to 1800 hrs 17/12/2024.
The forecast capacity reserve requirement is 745 MW.
The minimum capacity reserve available is 611 MW.
AEMO estimates the latest time at which it would need to intervene through an AEMO intervention event is 1400 hrs on 17/12/2024.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 17/12/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 122005 has been updated to the following:
[1.] From 1530 hrs 17/12/2024 to 1800 hrs 17/12/2024.
The forecast capacity reserve requirement is 914 MW.
The minimum capacity reserve available is 553 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations